A. Building permit fees shall be based on the total valuation of the proposed project as shown on the Salt Lake City consolidated fee schedule.
B. Plan review fees shall be sixty five percent (65%) of the building permit fees.
C. Fees to expedite building plan review as governed by section 18.20.050 of this title shall be two (2) times the standard building plan review fee.
D. Penalties for not obtaining permanent certificate of occupancy will be three hundred dollars ($300.00) for each month, after the initial thirty (30) day temporary certificate of occupancy, which has no additional cost associated with it; due before the first of the month and only allowed for up to three (3) renewals after the initial free thirty (30) day period. Partial months will not be refunded.
E. Fees for renewing expired plan review after one hundred eighty (180) days as governed by section 18.20.110 of this title shall be shown on the Salt Lake City consolidated fee schedule.
F. A fee shown on the Salt Lake City consolidated fee schedule shall be charged for each permit for fencing.
G. Other fees shall consist of electrical, mechanical and plumbing, and fire suppression and monitoring equipment inspection fees as shown on the Salt Lake City consolidated fee schedule. (Ord. 42-11, 2011)