17.44.100: INSPECTION OF SEWER LINES; CORRECTIONS:
The inspection of sewer lines between the POTW sewer main and within three feet (3') of the building foundation shall be under the direction of the director. The POTW shall be notified on a regular working day at least twenty four (24) hours in advance of the time the permittee requests inspection. The entire length of the building sewer, including the junction at the POTW sewer shall be fully exposed. Any portion of the work not done in accordance with these requirements and the instruction of the POTW, or its inspectors, shall be corrected promptly. There shall be no backfilling until the inspection is made and the work accepted. No certificate of inspection shall be issued until the work is satisfactorily performed and accepted. (Ord. 36-93 § 5, 1993: prior code § 37-4-11)