17.10.040 APPLICATION REVIEW AND REPORT.
   After acceptance of a complete application, the project shall be reviewed in accordance with the environmental review procedures of the California Environmental Quality Act (CEQA). The Community Development Director will consult with other departments as appropriate to ensure compliance with all provisions of the Municipal Code and other adopted policies and plans. The Community Development Director will prepare a report (the staff report) to the designated approving authority describing the project, along with a recommendation to approve, conditionally approve, or deny the application. The report shall be provided to the applicant prior to consideration of the entitlement request. The report may be amended as necessary or supplemented with additional information at any time prior to the hearing to address issues or information not reasonably known at the time the report is prepared. (Ord. 2010-02 § 1 (part), 2010)