107.6.2.2 Connection not feasible or not available.
Where a public combined or storm sewer is not available, or where connection thereto is not feasible, applicants shall submit:
1. Department of Environmental Protection or applicant certification of unavailability or non-feasibility.
(i) Certification issued by the Department of Environmental Protection that a public storm or combined sewer is not available or that connection thereto is not feasible. Such certification shall be on forms specified by such department (Department of Environmental Protection "house/site connection proposal application" or other form as specified in the rules of such department); or
(ii) Certification submitted by the applicant to the Department of Environmental Protection that a public storm or combined sewer is not available or that connection thereto is not feasible, in such cases where the availability and feasibility of connection to a public storm or combined sewer are allowed to be certified by the applicant pursuant to rules of such department. Certification shall be on forms specified by such department (Department of Environmental Protection "house/site connection proposal application" or other form as specified in the rules of such department); and
2. On-site disposal. A proposal for the design and construction of a system for the on-site disposal of stormwater conforming to the provisions of this code and other applicable laws and rules including but not limited to minimum required distances from lot lines or structures and subsoil conditions. Construction documents for such system shall be subject to the approval of the department.
107.6.3 Post-construction stormwater management facilities.
A post-construction stormwater management facility that is constructed as a part of a covered development project shall comply with the rules of the Department of Environmental Protection and with this code.
(L.L. 2017/097, 5/30/2017, eff. 6/1/2019; Am. L.L. 2020/091, 9/27/2020, eff. 3/26/2021)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2020/091.
107.7 Private sewers.
If private sewers are to be constructed pursuant to subdivision b of Section 1403 of the New York City Charter, a copy of the sewer plan shall be submitted.
107.8 Private sewage treatment plant.
If a private sewage treatment plant is to be constructed, a copy of plans approved by the Department of Health and Mental Hygiene and the Department of Environmental Protection shall be submitted.
107.9 Private stormwater or sewage disposal system.
If a private stormwater or sewage disposal system is to be installed, a site and subsoil evaluation indicating that the site and subsoil conditions comply with the applicable laws and rules shall be submitted in accordance with the provisions of Section 1705.27 of the New York City Building Code.
(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.
107.10 Energy efficiency.
Construction documents shall include compliance documentation as required by the New York City Energy Conservation Code.
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/085.