§ 28-104.11 Construction documents for sites that are covered development projects as defined in section 24-541 of the administrative code.
Construction documents for sites that are covered development projects as defined in section 24-541 of the administrative code shall comply with section 28-104.11.1 through 28-104.11.4.
(L.L. 2017/097, 5/30/2017, eff. 6/1/2019; Am. L.L. 2020/091, 9/27/2020, eff. 3/26/2021)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2020/091.
As used in this code in connection with provisions relating to the jurisdiction of the department of environmental protection, the terms covered development project, development activity, post-construction stormwater management facility, stormwater construction permit, stormwater maintenance permit, and stormwater pollution prevention plan or SWPPP shall have the same definitions as such terms are defined in subchapter 1 of chapter 5-A of title 24 of the administrative code.
(L.L. 2017/097, 5/30/2017, eff. 6/1/2019; Am. L.L. 2020/091, 9/27/2020, eff. 3/26/2021)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2020/091.
It shall be the duty of an applicant for construction document approval to determine whether the site of the proposed work is part of a covered development project and to disclose such information on construction documents. Failure to disclose such information on construction documents shall be a violation of this code.
(L.L. 2017/097, 5/30/2017, eff. 6/1/2019; Am. L.L. 2020/091, 9/27/2020, eff. 3/26/2021)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2020/091.
Applications for construction document approval shall include copies of any required stormwater construction permit issued by the department of environmental protection and the stormwater pollution prevention plan for the covered development project.
(L.L. 2017/097, 5/30/2017, eff. 6/1/2019)
Where the department finds after the approval of construction documents that the applicant failed to disclose the information required by this section, the department may revoke such approval and any associated work permits in accordance with the provisions of sections 28-104.2.10 and 28-104.2.10.1.
(L.L. 2017/097, 5/30/2017, eff. 6/1/2019)
An applicant shall retain one set of approved construction documents, submittal documents and any other documents required by department rule for a period of not less than six years from the date of completion of the permitted work.
(L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
Where an owner of a new or altered taller building is required by section 2113 of the New York city building code, section 801 of the New York city mechanical code or section 501 of the New York city fuel gas code to extend, alter or relocate an existing chimney or vent on an affected building, such work shall be filed under a separate application for the affected building.
(L.L. 2021/126, 11/7/2021, eff. 11/7/2022)