1353.12 ENFORCEMENT.
   (a)   If the City determines that a violation of the rules adopted under this code exist, the City may issue an immediate stop work order if the violator failed to obtain any federal, state, or local permit necessary for sediment and erosion control, earth movement, clearing, or cut and fill activity.
   (b)   All development areas may be subject to external inspections by the City Engineer to ensure compliance with the approved SWP3 or abbreviated SWP3.
   (c)   If an external inspection determines that operations are being conducted in violation of the approved SWP3 or abbreviated SWP3, the City Engineer may take action as detailed in Sections 1353.12 and 1353.13 of this chapter.
   (d)   After each external inspection, the City Engineer shall prepare and distribute a status report to the applicant.
   (e)   Failure to maintain and repair erosion and sediment controls per the approved SWP3 plan may result in the following escalation. The penalty is determined by the total number of violations per site even if the violations are for different BMPs.
      (1)   First Violation: The City Engineer will issue a Notice of Deficiency to the owner or operator. All controls are to be repaired or maintained per the SWP3 plan within three (3) days of the notification. If controls have not been corrected after this time, the Chief Building Official may issue a Stop Work Order for all activities until corrections have been made.
      (2)   Second Violation: The City Engineer may issue a formal Notice of Violation which includes a five hundred dollar ($500.00) administrative fee against the SWP3 Bond or site plan deposit. All controls are to be repaired or maintained per the approved SWP3 plan within three (3) days of the Notice of Violation. If controls have not been corrected after this time, the Chief Building Official may issue a Stop Work Order for all activities until corrections have been made.
      (3)   Third and subsequent violations: The Chief Building Official may issue a Stop Work Order for all construction activities and charge a one thousand dollar ($1,000) administrative fee against the SWP3 bond or site plan deposit. The Stop Work Order will be lifted once all controls are in compliance with the approved SWP3 plan.
   (f)   The City Engineer shall have the authority to make immediate on-site adjustments to the SWP3 in order to achieve compliance with this chapter.
   (g)   A final inspection will be made to determine if the criteria of this code has been satisfied and a report will be presented to the site operator on the site's compliance status.
   (h)   The City Engineer will monitor soil-disturbing activities for non-farm residential, commercial, industrial, or other non-farm purposes on land of less than one contiguous acre to ensure compliance required by these Rules.
(Ord. 23-O-002. Passed 1-3-23.)