1241.06   LOT CREATION IN THE AR-1 AND AR-2 ZONING DISTRICTS.
   Lots within the AR-1 and AR-2 Zoning Districts may be created under one of the following three development options:
   (1)   Division - Lots proposed to be created in accordance with the Base Density Division Option contained in the Zoning Ordinance may do so in accordance with the following procedures:
      (a)   A request for a certificate of approval of a plat of Division shall contain the following:
         i.   The proposed plat of Division; and
         ii.   Unexecuted deed or deeds granting any required street dedication necessary to satisfy the requirements of the Zoning Ordinance; and
         iii.   An unexecuted Private Roads Maintenance Agreement if private access easements are to be established.
         iv.   A letter signed by the Health Director evidencing conformance with applicable requirements of the County Health Department.
      (b)   The Director shall, within thirty (30) days after receipt of such plat and accompanying deeds, if applicable, review such plat and either execute the certificate of approval thereon or deny approval stating the specific reasons for such denial.
      (c)   In conducting such review, the Director shall determine whether such plat meets all of the requirements of the Zoning Ordinance and plat requirements contained in Chapter 8.103.8 of the FSM and Section 1241.06 of this chapter.
   (2)   Principal/Subordinate Subdivision Option. Lots proposed to be created in accordance with the Principal/Subordinate Subdivision Option contained in the Zoning Ordinance shall be developed in accordance with the following procedures.
      (a)   The creation of a single Subordinate Lot shall follow the procedures and requirements of the provisions of Section 1243.05.1
      (b)   The creation of more than one Subordinate Lot but less than 5 Subordinate Lots at a time shall follow the procedures and requirements of Preliminary/Record Plat requirements.
      (c)   The creation of more than 4 Subordinate Lots at a time shall follow the procedures and requirements of Preliminary Plat of Subdivision.
      (d)   The creation of Subordinate Lots intended for members of the immediate family as identified in Section 1243.04 shall follow the process and requirements associated with family subdivisions.
   (3)   Cluster Subdivision - Lots proposed to be created in accordance with the Cluster Subdivision provisions of the Zoning Ordinance shall be developed in accordance with the following procedures.
      (a)   The creation of a single cluster lot shall follow the procedures and requirements of the provisions of Section 1243.05.1 .
      (b)   The creation of five (5) lots or fewer shall follow the procedures and requirements for a Preliminary/Record Plat.
      (c)   The creation of more than 5 lots shall follow the procedures and requirements for a Preliminary Plat of Subdivision.
(Ord. 00-04. Passed 4-29-00; Ord. 06-16. Passed 12-5-06.)