§ 22-1201.   Completion of Improvements or Guarantee Thereof Prerequisite to Final Plan Approval.
   1.   No plan shall be finally approved unless the streets shown on such plan have been improved to a mud-free or otherwise permanently passable condition, or improved as may be required by this Chapter, and any walkways, curbs, gutters, street lights, fire hydrants, shade trees, water mains, sanitary sewers, storm sewers and other improvements as required by this Chapter have been installed in accordance with this Chapter. In lieu of the completion of any improvements required as a condition for the final approval of a plan, the developer shall provide for the deposit with the Township of financial security in an amount sufficient to cover the costs of such improvements or common amenities including, but not limited to, roads, stormwater detention and/or retention basins and other related drainage facilities, recreational facilities, open space improvements, or buffer or screen plantings which may be required.
   2.   When requested by the developer, in order to facilitate financing, the Board of Township Supervisors shall furnish the developer with a signed copy of a resolution indicating approval of the final plan contingent upon the developer obtaining a satisfactory financial security. The final plan or record plan shall not be signed nor recorded until the financial improvements agreement is executed. The resolution or letter of contingent approval shall expire and be deemed to be revoked if the financial security agreement is not executed within 90 days unless a written extension is granted by the Board of Township Supervisors; such extension shall not be unreasonably withheld and shall be placed in writing at the request of the developer.
   3.   Without limitation as to other types of financial security which the Township may approve, which approval shall not be unreasonably withheld, Federal or Commonwealth chartered lending institution irrevocable letters of credit and restrictive or escrow accounts in such lending institutions shall be deemed acceptable financial security for the purposes of this Section.
   4.   Such financial security shall be posted with a bonding company or Federal or Commonwealth chartered lending institution chosen by the party posting the financial security, provided said bonding company or lending institution is authorized to conduct such business within the Commonwealth.
   5.   Such bond, or other security shall provide for, and secure to the public, the completion of any improvements which may be required on or before the date fixed in the formal action of approval or accompanying agreement for completion of the improvements.
   6.   The amount of financial security to be posted for the completion of the required improvements shall be equal to 110% of the cost of completion estimated as of 90 days following the date scheduled for completion by the developer. Annually, the Township may adjust the amount of financial security by comparing the actual cost of the improvements which have been completed and the estimated cost for completion of the remaining improvements as of the expiration of the ninetieth day after either the original date scheduled for completion or a rescheduled date of completion. Subsequent to said adjustment, the Township may require the developer to post additional security in order to assure that the financial security equals said 110%.
   7.   The amount of financial security shall be based upon an estimate of the cost of completion of the required improvements, submitted by an applicant or developer and prepared by a professional engineer licensed as such by the Commonwealth of Pennsylvania. The engineer shall certify the amount of security to be a fair and reasonable estimate of such cost. The Board of Township Supervisors, upon the recommendation of the Township Engineer, may refuse to accept such estimate for good cause shown. If the applicant or developer and the Township are unable to agree upon an estimate, then the estimate shall be recalculated and recertified by another professional engineer licensed as such in the Commonwealth and chosen mutually by the Township and the applicant or developer. The estimate certified by the third engineer shall be presumed fair and reasonable, and shall be the final estimate. In the event a third engineer is so chosen, fees for the services of said engineer shall be paid equally by the Township and the applicant or developer.
   8.   If the party posting the financial security requires more than one year from the date of posting of the financial security to complete the required improvements, the amount of financial security may be increased by an additional 10% for each one year period beyond the first anniversary date from posting of financial security or to an amount not exceeding 110% of the cost of completing the required improvements as re- established on or about the expiration of the preceding 1-year period by using the above procedure.
   9.   In the case where development is projected over a period of years, the Board of Township Supervisors may authorize submission of final plan by section or stages of development subject to such requirements or guarantees as to improvements in future sections or stages of development as it finds essential for the protection of any finally approved section of the development.
   10.   As the work of installing the required improvements proceeds, the party posting the financial security may request the Board of Township Supervisors to release or authorize the release, from time to time, such portions of the financial security necessary for payment to the contractor or contractors performing the work. Any such requests shall be in writing addressed to the Board of Township Supervisors, and the Board of Township Supervisors shall have 45 days from receipt of such request within which to allow the Township Engineer to certify, in writing, to the Board of Township Supervisors that such portion of the work upon the improvements has been completed in accordance with the approved plan. Upon receipt of such certification the Board of Township Supervisors shall authorize release by the bonding company or lending institution of an amount as estimated by the Township Engineer fairly representing the value of the improvements completed or, if the Board of Township Supervisors fails to act within said 45-day period, the Board of Township Supervisors shall be deemed to have approved the release of funds as requested. The Board of Township Supervisors may, prior to final release at the time of completion and certification by its engineer, require retention of 10% of the estimated cost of the aforesaid improvements.
   11.   Where the Board of Township Supervisors accepts dedication of all or some of the requirements following completion, the Board of Township Supervisors may require the posting of financial security to secure structural integrity of said improvements as well as the functioning of said improvements in accordance with the design and specifications as depicted on the final plan for a term not to exceed 18 months from the date of acceptance of dedication. Said financial security shall be of the same type as otherwise required in this Section with regard to installation of such improvements, and the amount of the financial security shall not exceed 15% of the actual cost of installation of said improvements.
   12.   If financial security has been provided in lieu of the completion of improve ments required as a condition for the final approval of a plan as set forth in this Section, the Township shall not condition the issuance of building, grading or other permits relating to the erection or placement of improvements, including buildings, upon the lots or land as depicted upon the final plan upon actual completion of the improvements depicted upon the approved final plan. Moreover, if said financial security has been provided, occupancy permits for any building or buildings to be erected shall not be withheld following the improvement of the streets providing access to and from existing public roads to such building or buildings to a mud-free or otherwise permanently passable condition, as well as the completion of all other improvements as depicted upon the approved plan, either upon the lot or lots or beyond the lot or lots in question if such improvements are necessary for the reasonable use of or occupancy of the building or buildings.
(Ord. 2011-05, 3/14/2011, § 1201)