1. Copies of the final plan and supporting documentation shall be distributed by the Township agent to the following reviewing and advisory bodies for comment and report:
A. Township Public Works Director (3).
B. Township Sewer Authority (1).
C. Township Fire Chief/Fire Marshall (1).
D. Township Zoning Officer (2).
E. Township Planning Commission (1).
F. Township Records (1).
2. The applicant shall file copies of the plans, required fees and necessary related documents to:
A. York County Conservation District.
B. Appointed Township Engineer.
C. York County Planning Commission.
D. Pennsylvania Department of Transportation.
E. Pennsylvania Department of Environmental Protection.
3. Additionally, final plans shall be submitted to adjacent municipalities and governmental agencies or authorities identified in § 22-308 that may be affected by the plan.
4. Upon review of a subdivision or land development plan, the Township Engineer shall make comments and recommendations in writing to the Township Planning Commission and the Board of Township Supervisors.
5. During the course of the Planning Commission’s review of the final plan and prior to any action by the Board of Township Supervisors within the required 90-day period, the final plan may be revised by the applicant according to the procedure for preliminary plan revisions and as set forth in § 22-504 herein, and a new 90-day review period will begin as also set forth in § 22-504.
6. The Board of Township Supervisors shall render its decision and communicate it to the applicant in accordance with the requirements of § 22-309 of this Chapter.
(Ord. 2011-05, 3/14/2011, § 603)