§ 27-506.   Demolition.
   Demolition of any structure must be completed within three months of the issuance of a permit. Completion consists of tearing the structure down to grade, filling any resulting cavity to grade and removing all resulting material from the lot. A structure may be partly demolished only if a building remains and the demolition of the part is complete as aforesaid. All evidence of the structure which was demolished must be removed from the exterior surfaces of the building remaining.
(Ord. 2015-06, 9/28/2015)