846.07 CONSTRUCTION REQUIREMENTS AND PERMITS.
   (a)   The Zoning Administrator shall issue a building transmittal prior to the erection, construction or alteration, not to include maintenance as defined herein, of any permanent sign with the exception of those signs described in Section 846.04 and in Schedule D.
   (b)   The construction of any sign shall be subject to the requirements of the Eaton County Building Code. Sign building permits, if necessary, shall be issued on the basis of plans and applications approved by the Eaton County Building Department and shall authorize only the design and construction set forth in such approved plans and applications and no other design. A building transmittal issued by the Zoning Administrator is required for the issuance of a building permit by Eaton County.
(Ord. 2003-7. Passed 1-12-04; Ord. 2011-2. Passed 4-11-11.)