16.16.120 Submittal procedure.
   The final map as submitted shall be accompanied by:
   (A)   Traverse sheets and work sheets showing the closure, within the allowable limits of error, of the exterior boundaries and of each block and lot of the subdivision;
   (B)   Plans and specifications of all proposed improvements, together with the necessary improvement security;
   (C)   A copy of the protective covenants to be recorded;
   (D)   Plan checking fee;
   (E)   A soils report prepared by a registered civil engineer pursuant to the Subdivision Map Act. If such report indicates the presence of critically expansive soils or other soil problems which, if not corrected, would lead to structural defects, a soils investigation of each lot in the subdivision shall be required. The engineer shall sign the final map indicating that a soils report has been prepared.
(`78 Code, § 16.16.120.) (Ord. 1522 § 2 (part), 1978.)