1315.15 INSPECTIONS.
   In any new building or addition, immediately upon completion of those portions of the installation which are thereafter to be concealed or covered, the plumbing contractor shall notify the Plumbing Inspector that such portions of the installation are ready for inspection. No plumbing contractor or person under his direct control shall drywall or cover up any plumbing work before such work has been inspected and the building permit card stamped approved. The Plumbing Inspector shall make inspection within two working days after notice. The final inspection on new installations and repair, replacement or conversion work shall be made upon completion of such work. (Ord. 258-2001. Passed 12-10-01.)