To receive final inspection and acceptance of any project, or portion thereof, the following must be completed and provided to the Storm Water Program Manager:
(a) Final stabilization must be achieved and all permanent storm water management practices must be installed and made functional, as determined by the Storm Water Program Manager and per the approved Comprehensive Storm Water Management Plan.
(b) An as-built certification, including a survey and inspection, must be sealed, signed and dated by a professional engineer and a professional surveyor with a statement certifying that the storm water management practices, as designed and installed, meet the requirements of the Comprehensive Storm Water Management Plan approved by the Storm Water Program Manager. In evaluating this certification, the Storm Water Program Manager may require the submission of a new set of storm water practice calculations if he or she determines that the design was altered significantly from the approved Comprehensive Storm Water Management Plan. The as-built survey must provide the location, dimensions, and bearing of such practices and include the entity responsible for long-term maintenance as detailed in the inspection and maintenance agreement.
(c) A copy of the complete and recorded inspection and maintenance agreement as specified in Section 1060.08 must be provided to the Storm Water Program Manager.
(Ord. 88-2012. Passed 6-25-12; Ord. 26-2013. Passed 3-25-13.)