8.20.050 STORMWATER CONTROL PLAN REQUIRED.
   A.   Every application for a development project that is subject to the development runoff requirements in the City's NPDES permit shall be accompanied by a stormwater control plan that meets the criteria in the most recent version of the Contra Costa Clean Water Program Stormwater C.3. Guidebook.
   B.   Implementation of an approved stormwater control plan and submittal of an approved stormwater control operation and maintenance plan by the applicant shall be a condition precedent to the issuance of a certificate of occupancy for a project subject to this section.
   C.   All stormwater management facilities shall be designed in a manner to minimize the need for maintenance and reduce the chances of failure. Design guidelines are outlined in the guidebook.
   D.   All stormwater management facilities shall be maintained according to the guidebook and the approved stormwater control operation and maintenance plan. The person(s) or organization(s) responsible for maintenance shall be designated in the plan. Unless a different time period is provided for in the plan, those responsible for maintenance shall inspect the stormwater management facility at least annually. The plan shall also describe how the maintenance costs will be funded. Upon the failure of a responsible person to maintain a stormwater management facility in accordance with this chapter or the plan, the City may perform the maintenance and recover its costs from the responsible person as provided in Sections 8.20.170 and 8.20.180.
   E.   For access to stormwater management facilities for inspections and maintenance, recorded covenants or easements shall be provided by the property owner for access by the City, the Contra Costa Mosquito and Vector Control District, and the Regional Water Quality Control Board.
(Ord. 2017-13 § 3, 2017; Ord. 2004-16 § 1(part), 2004).