Loading...
Fees for building permits are as follows:
(a) New Construction or Additions.
Category | Residential Accessory Buildings/Structures | Residential | Commercial | Industrial |
Building | 30¢/sq. ft. | 65¢/sq. ft. | $2.32/sq. ft. | $2.32/sq. ft. |
Plumbing | $20/fixture $60 drain tile, $60 underfloor piping ($75 minimum) | $20/fixture, $60 drain tile, $60 underfloor piping ($75 minimum) | $20/fixture, $60 drain tile, $60 underfloor piping ($75 minimum) | $20/fixture, $60 drain tile, $60 underfloor piping ($75 minimum) |
Electrical | $90/service or submain, plus $10/circuit ($75 minimum) | $90/service or submain, plus $10/circuit ($75 minimum) | $90/service or submain, plus $10/circuit ($75 minimum) | $90/service or submain, plus $10/circuit ($75 minimum) |
HVAC | $1/1,000 BTU | $1/1,000 BTU | $1/1,000 BTU | $1/1,000 BTU |
Swimming pools; except inflatable or moveable kiddie pools 36" deep or less | $350 | |||
Structures; such as fences, gates, walkways | $75 | $75 | $75 | |
Construction water | $200 if needed | $200 | $200 | $200 |
Building plan review (non-refundable) | $60 | $300 | $300 | $300 |
Accessory structure plan review | $60 | $60 | $60 | |
Site improvement; except for one single-family home | 5% of site improvement costs | 5% of site improvement costs | 5% of site improvement costs | 5% of site improvement costs |
Zoning Review Fee (if a zoning review is requested by the applicant or required by the Community Development Director as part of the permitting process) | $75 | $75 | $75 | $75 |
Note: All fees shall be double for work started without permit per Village Code Section 210.03.
Note: Any actual Village costs in excess of set fee amount is added to permit fee per Village Code Chapter 208.
(b) Remodeling of Existing Structures. In remodeling, where no square footage is added to the existing structure, the following permit fees shall apply, along with one-half the applicable plan review application fee set forth in subsection (a) hereof. For remodeling in which square footage is added, the fees shall be as set forth in subsection (a).
Category | Residential Accessory | Residential | Commercial | Industrial |
Building | 15¢/sq. ft. | 35¢/sq. ft. | $1.16/sq. ft. | $1.16/sq. ft. |
Plumbing | $20/fixture, $60 drain tile, $60 underfloor piping ($75 minimum) | $20/fixture, $60 drain tile, $60 underfloor piping ($75 minimum) | $20/fixture, $60 drain tile, $60 underfloor piping ($75 minimum) | $20/fixture, $60 drain tile, $60 underfloor piping ($75 minimum) |
Electrical | $90/service or submain, plus $10 per circuit ($75 minimum) | $90/service or submain, plus $10 per circuit ($75 minimum) | $90/service or submain, plus $10 per circuit ($75 minimum) | $90/service or submain, plus $10 per circuit ($75 minimum) |
HVAC | $1/1,000 BTU | $1/1,000 BTU | $1/1,000 BTU | $1/1,000 BTU |
Structures; such as fences, gates, walkways | $75 | $75 | $75 | |
Re-roofing | $75 | $75 | $75 | $75 |
Building plan review (non-refundable) | $60 | $300 | $300 | $300 |
Accessory structure plan review | $60 | $60 | $60 | |
Site improvement; except for one single- family home | 5% of site improvement costs | 5% of site improvement costs | 5% of site improvement costs | 5% of site improvement costs |
Zoning Review Fee (if a zoning review is requested by the applicant or required by the Community Development Director as part of the permitting process) | $75 | $75 | $75 | $75 |
Note: All fees shall be double for work started without permit per Village Code Section 210.03.
Note: Any actual Village costs in excess of set fee amount is added to permit fee per Village Code Chapter 208.
(c) Inspections. The fee for a building inspection, other than a plumbing or electrical inspection, shall be seventy-five dollars ($75.00). The fee for a plumbing or electrical inspection shall be one hundred dollars ($100.00). When a re-inspection is required, due to the previous inspection not being approved by the Village, the fees shall be one hundred twenty-five dollars ($125.00) for any such re-inspection.
(Ord. 1986-28. Passed 8-11-86; Ord. 1998-11. Passed 4-27-98; Ord. 1998-22. Passed 7-13-98; Ord. 2000-14. Passed 5-8-00; Ord. 2001-35. Passed 8-27-01; Ord. 2005-43. Passed 12-12- 05; Ord. 2006-37. Passed 8-14-06; Ord. 2009-23. Passed 10-26-09; Ord. 2019-14. Passed 7-8-19.)
A structure which does not clearly fall into any of the categories enumerated in Section 1444.05 shall be considered an accessory building unless it is determined that a special category and fees therefore shall be established by Council.
(Ord. 1974-16. Passed 11-25-74.)
A permit, under which the proposed work authorized by said permit is not commenced within six months of the date of issuance or not completed within twelve months after the date of issuance, shall expire, and no work under the permit shall commence thereafter. Said expired permit, however, may be renewed as set forth below, provided the proposed work is still in conformance with the Village Code and provided the owner and contractor estimate and the Village agrees that the work can be completed within the renewal period. Said permits for construction of new buildings where all work on exterior walls and roof is completed and inspected by the Village may be renewed in increments of three months with commencement and completion of the work to take place within the renewal period. All other permits may be renewed in increments of six months with commencement and completion of the work to take place within the renewal period. Fees for said permit renewals shall include a plan review fee if needed to determine compliance with Village Code, as well as the other fees as required in this chapter, with said fees being prorated based on the length of renewals periods being approved. For example, if a permit is renewed for one three-month period, then the renewal fee would be three-twelfths of the original permit fee.
(Ord. 2009-08. Passed 4-13-09.)