(A) No later than 30 days after acceptance of a surface mining permit application as complete, the director shall notify the State Department of Conservation of the filing of the application.
(B) No later than 30 days after acceptance of a surface mining permit application as complete, the director shall notify the State Department of Transportation of the filing of the application if both of the following conditions are satisfied:
(1) The proposed mining operations are in the 100-year flood plain of any stream, as shown in Zone A of the Flood Insurance Rate Maps issued by the Federal Emergency Management Agency; and
(2) The proposed mining operations are within one mile, upstream or downstream, of any State highway bridge.
(Ord. No. 2579)