A. Permit Required: No unauthorized person shall uncover, make any connection with or opening into, use, alter or disturb any public sewer or appurtenance thereof without first obtaining a written permit from the City.
B. Application For Permit: The application for the permit shall set forth the location and description of the property to be connected with the sewer system and the purpose for which the sewer is to be used, and shall be supplemented by any plans, specifications, or other information considered pertinent. (Prior Code § 6-3-4)
C. Permit Fee: The applicant shall pay a fee to the City as established in section 3-1-2 of this Code to cover the cost of issuing the sewer connection permit and supervising, regulating and inspecting the work. (Prior Code § 6-3-4; amd. 2018 Code)
D. Time For Completion Of Construction: The permit shall require the applicant to complete construction and connection of the building sewer to the public sewer within ninety (90) days after the issuance of the permit; except, that when the applicant makes sufficient showing that due to conditions beyond the applicant's control or due to peculiar hardship, such time period is inequitable or unfair, an extension of time within which to comply with the provisions herein may be granted.
E. Revocation Of Permit: Any sewer connection permit may be revoked at any time for a violation of this chapter. (Prior Code § 6-3-4)