1241.07 ACTION BY PLANNING COMMISSION ON CONDITIONAL USES.
   (a)   Required Action. Upon review of a conditional use application, the Planning Commission shall take one (1) of the following actions:
      (1)   If the proposed conditional use is determined by the Planning Commission to be appropriate and in conformance with the review criteria outlined in Chapter 1287, the Planning Commission shall approve the conditional use. As part of the approval, the Planning Commission may prescribe reasonable requirements or conditions on the proposed use to ensure that the development conforms to the intent and purposes of Chapter 1287. The Planning Commission may approve the application for a conditional use and subsequently approve the final site plan.
      (2)   The Planning Commission shall deny the application if the Planning Commission concludes that, if completed as proposed, the development will not be in compliance with the requirements of this Zoning Code.
   (b)   Failure of the Planning Commission to Act. If the Planning Commission fails to act within three (3) regularly scheduled meetings from the date that the application was deemed complete, or an extended period as may be agreed upon, then the application shall be deemed to have been approved.
(Ord. 2010-059. Passed 3-7-11.)