(a) Runoff Rate: The peak runoff rate from the development area shall not be greater after development than it was before development. The applicant shall provide calculations proving no increase in the runoff rates from the one (1), two (2), five (5), ten (10), twenty-five (25), fifty (50) and one hundred (100) year storms.
(b) Runoff Volume: Increases in the runoff volume shall be offset by further restricting runoff rates. Based on the increase in runoff volume, the applicant shall determine the critical storm for the development area. The runoff rate from the critical storm shall be restricted to the one (1) year predevelopment storm runoff rate. The critical storm shall be calculated as follows:
(1) Determine the total volume of runoff from a one-year frequency, twenty-four hour storm, occurring on the development area before and after development.
(2) From the volumes in paragraph (a) determine the percent of increase in volume of runoff due to development according to the equation (Q after divided by the Q before) X 100 and, using this percentage, select the critical storm from this table:
Table 4: Critical Storm Selection
The Percentage Increase in Volume of Runoff is: | ||
Equal to or Greater Than | And Less Than | The 24-Hour “Critical Storm” For Discharge Will Be |
0 | 10 | 1 Year |
10 | 20 | 2 Years |
20 | 50 | 5 Years |
50 | 100 | 10 Years |
100 | 250 | 25 Years |
250 | 500 | 50 Years |
500 | --- | 100 Years |
(c) Detention Or Retention Basin Exemption For Redevelopment Or For Expansion Of Existing Facilities:
(1) For any development regulated by this chapter, the construction of a detention or retention basin may not be required for the development if the post-development peak discharge for a 100 year frequency 24 hour storm increases the existing peak discharge by one (1) cubic foot per second or less using the TR-55 method of calculation or other method approved by the Community Engineer. The Community Engineer can waive this requirement if existing storm sewers and drainage structures can safely handle the expected increase in flow.
(2) Only one (1) exemption will be allowed per parcel. Any subsequent expansion must provide for detention or retention and must include the previously exempted area.
(d) Where the Community Engineer determines that site constraints exist in a manner that compromises the intent of this chapter to improve the management of storm water runoff as established in this section, practical alternatives may be used to result in an improvement of water quality and/or a reduction of storm water runoff. Such alternatives must be in keeping with the intent and likely cost of those measures that would otherwise be required to meet the objectives of this section. When possible, all practical alternatives shall be implemented within the drainage area of the proposed development project. Practical alternatives can include, but are not limited to:
(1) Fees shall be paid in an amount specified by the Community Engineer. These fees shall be applied by the Community to storm water management practices that reduce existing storm water runoff.
(2) Implementation of off-site storm water management practices.
(3) Watershed or stream restoration.
(4) Retrofitting of an existing storm water management practice.
(5) Other practices approved by the Community Engineer in keeping with the intent of this section.
(Ord. 2009-26. Passed 5-20-09.)
(a) Ohio Dam Safety Laws: The provisions of the Ohio Dam Safety Laws shall be followed. Proof of compliance with the Ohio Dam Safety Law administered by the ODNR Division of Water shall be, but is not limited to, a copy of the ODNR Division of Water permit number or a copy of the project approval letter from the ODNR Division of Water or a letter from the site owner explaining why the Ohio Dam Safety Law is not applicable. The written proof will be provided to the Community Engineer before a construction permit will be issued.
(b) NPDES Permits: The provisions of the National Pollutant Discharge Elimination System (NPDES) Permits, issued by the Ohio EPA, shall be followed. Proof of compliance shall be, but is not limited to, a copy of the Ohio EPA NPDES Permit number or a letter from the site owner explaining why the NPDES Permit is not applicable. The written proof will be provided to the Community Engineer before a construction permit will be issued.
(c) Federal And State Wetland Permits: The provisions of the U.S. Army Corps of Engineers dredge and fill permits for federally-protected wetlands shall be followed. The provisions of Ohio EPA's Isolated Wetlands Permits shall also be followed. Wetlands and other waters of the United States shall be delineated by protocols accepted by the U.S. Army Corps of Engineers and the Ohio EPA at the time of the application of these regulations. Written proof of compliance with both permit programs will be provided to the Community Engineer before a construction permit will be issued. Proof of compliance shall be, but is not limited to, the following:
(1) A copy of the U.S. Army Corps of Engineers Individual Permit, if required for the project, showing project approval and any restrictions that apply to site activities; or
(2) A site plan showing that any proposed fill of waters of the United States conforms to the general and specific conditions specified in the applicable Nationwide Permit; or
(3) A letter from the site owner verifying that a qualified professional has surveyed the site and found no wetlands or other waters of the United States. Such a letter shall be noted on site plans submitted to the Community.
(Ord. 2009-26. Passed 5-20-09.)
No person shall violate, or cause, or knowingly permit to be violated, any of the provisions of these regulations, or fail to comply with any such provisions or with any lawful requirements of any public authority made pursuant to these regulations, or knowingly use or cause or permit the use of any lands in violation of these regulations or in violation of any permit granted under these regulations. (Ord. 2009-26. Passed 5-20-09.)
(a) Whoever violates or fails to comply with any provision of this regulation is guilty of a misdemeanor of the first degree and shall be fined no more than one thousand dollars ($1,000.00) or imprisoned for no more than one hundred eighty (180) days, or both, for each offense.
(b) A separate offense shall be deemed committed each day during or on which a violation or noncompliance occurs or continues.
(c) Upon notice from the Community Engineer, or designated representative, that work is being performed contrary to this regulation, such work shall immediately stop. Such notice shall be in writing and shall be given to the owner or person responsible for the development area, or person performing the work, and shall state the conditions under which such work may be resumed; provided, however, in instances where immediate action is deemed necessary for public safety or the public interest, the Community Engineer may require that work be stopped upon verbal order pending issuance of the written order.
(d) The imposition of any other penalties provided herein shall not preclude the Community, by or through its Law Director and/or any of their assistants, from instituting an appropriate action or proceeding in a Court of Proper Jurisdiction to prevent an unlawful development or to restrain, correct or abate a violation, or to require compliance with the provisions of this regulation or other applicable laws, or ordinances, rules or regulations or the orders of the Community Engineer.
(Ord. 2009-26. Passed 5-20-09.)
All permanent storm water, soil erosion, other wastes control, and water quality practices not specifically waived by the Community shall be constructed prior to the granting of the Final Plat Approval. Upon the request of the owner, the Community may defer the construction or installation of a permanent storm water, soil erosion, sediment, or other wastes control or water quality practice prior to the approval of the final plat where, in the Community Engineer's judgment, such proper construction or installation is not immediately necessary for the protection of the public health and safety; and where the prior installation or construction of such improvement would constitute an undue hardship on the owner because in the case of new vegetation or weather conditions, or because in the case of concrete, building construction could cause cracking and excessive wear and tear on new structures. In such event, the Community shall require a Security Bond, Escrow Account, Certified Check or Cash to guarantee that such deferred improvements will be properly constructed or installed within an agreed specified time, but not to exceed six (6) months after the filing of such final plat.
The owner will provide a maintenance guarantee for all permanent improvements, and soil erosion, wastes controls, and water quality practices.
The Community shall require a Security Bond, Escrow Account, Certified Check or Cash to guarantee that the planned temporary and permanent soil erosion, sediment, and other wastes controls and water quality practices will be constructed and removed in a timely manner, as determined by the Community Engineer.
(a) The Guarantee: The guarantee of both performance and maintenance will be in the form of a Security Bond, Escrow Account, Verified Check or Cash. The Security Bond, Escrow Account, Verified Check or Cash will be used by the Community to complete any guaranteed construction or removal of improvements or temporary and permanent soil erosion, sediment, and other wastes control practices that are not adequately completed, maintained or removed by the owner in a timely manner, as determined by the Community Engineer. The Security Bond, Escrow Account, Verified Check or Cash will be in the total amount of both the performance guarantee and the maintenance guarantee. Ohio municipalities and counties may require performance bonds or other guarantees for water management improvement as stated in Ohio R.C. Chapter 711.101.
(1) Security Bond, Escrow Account, Verified Check or Cash shall be deposited with the Community prior to review by the Community Engineer and/or its consultants to cover professional services of the Community Engineer, Building Commissioner, Zoning Inspector and/or other experts required by the Community Engineer, Community Council, Mayor or Review Boards.
(2) No soil disturbing activities shall be permitted until a Security Bond, Escrow Account, Verified Check or Cash has been posted to the satisfaction of the Community Engineer sufficient for the Community to perform the obligations otherwise to be performed by the owner or person responsible for the development area as stated in this regulation, and to allow all work to be performed as needed in the event that the owner or person responsible for the development area fails to comply with the provisions of this regulation. The Security Bond, Escrow Account, Verified Check or Cash shall be released only after all work required by this regulation has been completed to the satisfaction of the Community Engineer and all permit and inspection fees required by these regulations have been paid in full.
(3) No project subject to this regulation shall commence without the Construction Site Conservation Plan having been approved by the Community Engineer.
(b) Performance Guarantee: The furnishing of a performance guarantee will be maintained in an amount of not less than 120% of the estimate approved by the Community Engineer, of installation of the deferred improvements.
(c) Maintenance Guarantee: The maintenance guarantee shall be maintained for a period of not less than 2 (two) years after final acceptance of the storm water, soil erosion, sediment, and other wastes control practices in an amount equal to 20% of the estimate approved by the Community Engineer, of the construction and, where necessary, removal of such practices.
(d) Time Extension: The Community Engineer may extend for cause the time allowed for the installation of the improvements for which the performance guarantee has been provided with the receipt of a written request from the owner.
(e) Completion: Upon completion of the construction of improvements or temporary and/or permanent, soil erosion, sediment, and other wastes control practices and the removal of the temporary soil erosion, sediment, and other wastes control practices for which the performance guarantee has been provided the owner shall notify the Community Engineer of this fact.
(f) Inspection: The Community will not release the Security Bond, Escrow Account, Verified Check or Cash guarantee until the Community Engineer has inspected the site to ensure that the guaranteed item(s) have been completed and/or removed.
(g) Slow Release Devices: Performance and maintenance guarantees will be maintained on the temporary sediment removal slow release devices installed in detention and retention basins until the entire site has reached final soil stabilization. Final stabilization in single-family residential developments is when 90% of the homes are constructed with their lawns completely installed and any remaining unbuilt lots having been permanently stabilized with a uniform ground cover at a growth density of 80% or better.
(h) Release: The Construction Maintenance Guarantee shall not be released by the Community until all temporary soil erosion and sediment control practices that are no longer needed have been removed, properly disposed of and any trapped sediment has been stabilized.
(Ord. 2009-26. Passed 5-20-09.)
(a) This plan will be combined with the Post-Construction Water Quality, Riparian Setback and Wetland Setback Plans that have also been developed for the site.
(b) Plans developed by the site owners and approved by the Community in accordance with this regulation do not relieve the site owner of responsibility for obtaining and complying with all other necessary permits and/or approvals from federal, state, county, and local agencies and departments. If requirements vary, the most stringent requirement shall be followed. Plans submitted to the Community Engineer for review and approval, shall be accompanied by all other required permits and documentation relevant to the project, including but not limited to the permits required and issued by the US Army Corps of Engineers, Ohio EPA and ODNR Division of Water.
If the Community will be requiring that the local soil and water conservation district (SWCD) review the plans, the Community should first discuss this issue and how to implement the plan reviews with the local SWCD. It should be noted that only the Ohio EPA and the local communities can state that any plans or activities meet their regulations and rules.
(c) The application must include a letter or report from the local county SWCD that states that the Construction Site Conservation Plan, the Riparian and Wetland Setback Plan and the Post-construction Water Quality Plan have been reviewed for consistency with Ohio EPA and local regulations.
(d) Five (5) sets of the plans and necessary data required by this regulation shall be submitted to the Community Engineer with text material being submitted on 8.5 by 11 inch paper and drawings on no larger than 24 by 36 inch sized paper. Submittals shall include:
(1) At the preliminary plan approval request, the preliminary plans only need to show all of the following existing and planned features: streams, water bodies, wetlands, riparian and wetland setback areas, permanent BMPs and storm water management detention and retention basins.
(2) At the improvement plan approval request, the entire Comprehensive Storm Water Management Plan must be submitted.
(e) The Community Engineer shall review the plans, including the review report from the local county SWCD, and shall approve or return these with comments and recommendations for revisions within thirty (30) working days after receipt of the plan as described above. A plan rejected because of deficiencies shall receive a report stating specific problems. At the time of receipt of a revised plan, another thirty (30) day review period shall begin.
(f) Approved plans shall remain valid for two (2) years from the date of approval. After two (2) years the plan(s) approval automatically expires.
(g) No soil disturbing activity shall begin before all necessary local, county, state and federal permits have been granted to the owner or operator.
(h) The Community will do construction inspections until the site reaches final stabilization as determined by the Community Engineer.
(Ord. 2009-26. Passed 5-20-09.)
(a) APPROVING AUTHORITY: The official responsible for administering the applicable program(s).
(b) BEST MANAGEMENT PRACTICE (BMP): Any practice or combination of practices that is determined to be the most effective, practicable (including technological, economic, and institutional considerations) means of preventing or reducing the amount of pollution generated by non point sources of pollution to a level compatible with water quality goals. BMPs may include structural practices, conservation practices and operation and maintenance procedures.
(c) CERTIFIED PROFESSIONAL IN EROSION AND SEDIMENT CONTROL (CPESC): A person that has subscribed to the Code of Ethics and have met the requirements established by the CPESC Council of Certified Professional In Erosion and Sediment Control, Inc. to be a Certified Professional in Erosion and Sediment Control.
(d) CHANNEL: A natural stream that conveys water, or a ditch or channel excavated for the natural flow of water.
(e) CONCENTRATED STORM WATER RUNOFF: Surface water runoff which converges and flows primarily through water conveyance features such as swales, gullies, waterways, channels or storm sewers, and which exceeds the maximum specified flow rates of filters or perimeter controls intended to control sheet flow.
(f) CONSERVATION: The wise use and management of natural resources.
(g) CUT AND FILL SLOPES: A portion of land surface or area from which soil material is excavated and/or filled.
(h) DENUDED AREA: A portion of land surface on which the vegetation or other soil stabilization features have been removed, destroyed or covered, and which may result in or contribute to erosion and sedimentation.
(i) DETENTION BASIN: A storm water management pond that remains dry between storm events. Storm water management ponds include a properly engineered/designed volume which is dedicated to the temporary storage and slow release of runoff waters.
(j) DEVELOPMENT AREA: Any tract, lot, or parcel of land, or combination of tracts, lots or parcels of land, which are in one ownership, or are contiguous and in diverse ownership, where earth-disturbing activity is to be performed.
(k) DITCH: An excavation, either dug or natural, for the purpose of drainage or irrigation, and having intermittent flow.
(l) DUMPING: The grading, pushing, piling, throwing, unloading or placing of soil or other material.
(m) EARTH DISTURBING ACTIVITY: Any grading, excavating, filling, or other alteration of the earth's surface where natural or man-made ground cover is destroyed.
(n) EARTH MATERIAL: Soil, sediment, rock, sand, gravel, and organic material or residue associated with or attached to the soil.
(o) EROSION: The process by which the land surface is worn away by the action of water, wind, ice or gravity.
(p) EXISTING: In existence at the time of the passage of these regulations.
(q) FREQUENCY STORM: A rainfall event of a magnitude having a specified average recurrence interval and is calculated with Natural Resources Conservation Service, USDA Type II twenty-four hour curves or depth-duration frequency curves.
(r) GRADING: Earth disturbing activity such as excavation, stripping, cutting, filling, stockpiling, or any combination thereof.
(s) GRUBBING: Removing, clearing or scalping material such as roots, stumps or sod.
(t) LARGER COMMON PLAN OF DEVELOPMENT OR SALE: A contiguous area where multiple separate and distinct construction activities may be taking place at different times on different schedules under one plan.
(u) LANDSLIDE: The rapid mass movement of soil and rock material downhill under the influence of gravity in which the movement of the soil mass occurs along an interior surface of sliding.
(v) LOCAL COUNTY SWCD: The local county Soil and Water Conservation District.
(w) NATURAL RESOURCES CONSERVATION SERVICE (NRCS): An agency of the United States Department of Agriculture, formerly known as the Soil Conservation Service (SCS).
(x) NPDES PERMIT: A National Pollutant Discharge Elimination System Permit issued by Ohio EPA under the authority of the USEPA, and derived from the Federal Clean Water Act.
(y) OHIO EPA: The Ohio Environmental Protection Agency.
(z) ORDINARY HIGH WATER MARK: The point of the bank or shore to which the presence and action of surface water is so continuous as to leave a district marked by erosion, destruction or prevention of woody terrestrial vegetation, predominance of aquatic vegetation, or other easily recognized characteristic.
(aa) OUTFALL: An area where water flows from a structure such as a conduit, storm sewer, improved channel or drain, and the area immediately beyond the structure which is impacted by the velocity of flow in the structure.
(bb) PERSON: Any individual, corporation, partnership, joint venture, agency, unincorporated association, municipal corporation, township, county, state agency, the federal government, or any combination thereof.
(cc) PROFESSIONAL ENGINEER: A person registered in the State of Ohio as a Professional Engineer, with specific education and experience in water resources engineering, acting in strict conformance with the Code of Ethics of the Ohio Board of Registration for Engineers and Surveyors.
(dd) REDEVELOPMENT: The demolition or removal of existing structures or land uses and construction of new ones.
(ee) RETENTION BASIN: A storm water management pond that maintains a permanent pool of water. These storm water management ponds include a properly engineered/designed volume dedicated to the temporary storage and slow release of runoff waters.
(ff) RIPARIAN AREA: Naturally vegetated land adjacent to watercourses which, if appropriately sized, helps to stabilize streambanks, limit erosion, reduce flood flows, and/or filter and settle out runoff pollutants, or which performs other functions consistent with the purposes of these regulations.
(gg) RIPARIAN SETBACK: Those lands within the Community which are alongside streams where earth disturbing activities will not take place and natural vegetation will not be removed.
(hh) SEDIMENT: Solid material, both mineral and organic, that is in suspension, is being transported, or has been moved from its site of origin by wind, water, gravity or ice, and has come to rest on the earth's surface either on dry land or in a body of water.
(ii) SEDIMENT SETTLING POND: A temporary Sediment Pond that releases runoff at a controlled rate. It is designed to slowly release runoff, detaining it long enough to allow most of the sediment to settle out of the water. The outlet structure is usually a designed pipe riser and barrel. The entire structure is removed after construction. Permanent storm water detention structures can be modified to function as temporary Sediment Basins.
(jj) SEDIMENT CONTROL: The limiting of sediment being transported by controlling erosion or detaining sediment-laden water and, allowing the sediment to settle out.
(kk) SEDIMENT BARRIER: A sediment control device such as a geotextile Silt Fence or a grass Filter Strip, usually capable of controlling only small flow rates. (Straw bale barriers are not acceptable.)
(ll) SEDIMENT POLLUTION: A failure to use management or conservation practices to control wind or water erosion of the soil and to minimize the degradation of water resources by soil sediment in conjunction with land grading, excavating, filling, or other soil disturbing activities on land used or being developed for commercial, industrial, residential, or other purposes.
(mm) SENSITIVE AREA: An area or water resource that requires special management because of its susceptibility to sediment pollution, or because of its importance to the well-being of the surrounding communities, region, or the state and includes, but is not limited to, the following:
(1) Ponds, wetlands or small lakes with less than five acres of surface area;
(2) Small streams with gradients less than ten feet per mile with average annual flows of less than 3.5 feet per second containing sand or gravel bottoms.
(3) Drainage areas of a locally or Ohio designated Scenic River.
(4) Riparian and wetland areas.
(nn) SETTLING POND: A runoff detention structure, such as a Sediment Basin or Sediment Trap, which detains sediment-laden runoff, allowing sediment to settle out.
(oo) SHEET FLOW: Water runoff in a thin uniform layer or rills and which is of small enough quantity to be treated by sediment barriers.
(pp) SLIP: A landslide as defined under "Landslides."
(qq) SLOUGHING: A slip or downward movement of an extended layer of soil resulting from the undermining action of water or the earth disturbing activity of man.
(rr) SOIL: Unconsolidated erodible earth material consisting of minerals and/or organics.
(ss) SOIL CONSERVATION SERVICE, USDA: The federal agency now titled the "Natural Resources Conservation Service," which is an agency of the United States Department of Agriculture.
(tt) SOIL EROSION AND SEDIMENT CONTROL PLAN: A written and/or drawn soil erosion and sediment pollution control plan to minimize erosion and prevent off-site sedimentation throughout all earth disturbing activities on a development area.
(uu) SOIL EROSION AND SEDIMENT CONTROL PRACTICES: Conservation measures used to control sediment pollution and including structural practices, vegetative practices and management techniques.
(vv) SOIL STABILIZATION: Vegetative or structural soil cover that controls erosion, and includes permanent and temporary seeding, mulch, sod, pavement, etc.
(ww) SOIL SURVEY: The official soil survey produced by the Natural Resources Conservation Service, USDA in cooperation with the Division of Soil and Water Conservation, ODNR and the local Board of County Commissioners.
(xx) STORM WATER CONTROL STRUCTURE: Practice used to control accelerated storm water runoff from development areas.
(yy) STORM WATER CONVEYANCE: All storm sewers, channels, streams, ponds, lakes, etc., used for conveying concentrated storm water runoff, or for storing storm water runoff.
(zz) STORM WATER POLLUTION PREVENTION PLAN (SWP3): The plan required by Ohio EPA to meet the requirements of its National Pollutant Discharge Elimination System (NPDES) Permit program for construction activities.
(aaa) STREAM: A body of water running or flowing on the earth's surface, or a channel with a defined bed and banks in which such flow occurs. Flow may be seasonally intermittent.
(bbb) UNSTABLE SOIL: A portion of land surface or area which is prone to slipping, sloughing or landslides, or is identified by Natural Resources Conservation Service methodology as having a low soil strength.
(ccc) USEPA: The United States Environmental Protection Agency.
(ddd) WASTEWATER: Any water that is contaminated with gasoline, fuel oil, hydrocarbon based chemicals, paint, paint washing liquids or other paint wastes, sanitary wastes, or any other Ohio EPA regulated contaminants.
(eee) WATERCOURSE: Any natural, perennial, or intermittent channel with a defined bed and banks, stream, river or brook.
(fff) WATER RESOURCES: All streams, lakes, ponds, wetlands, water courses, waterways, drainage systems, and all other bodies or accumulations of surface water, either natural or artificial, which are situated wholly or partly within, or border upon this state, or are within its jurisdiction, except those private waters which do not combine or affect a junction with natural surface waters.
(ggg) WETLAND: Those areas that are inundated or saturated by surface or ground water at a frequency and duration sufficient to support, and that under normal circumstances, do support a prevalence of vegetation typically adapted for life in saturated soil conditions, including swamps, marshes, bogs, and similar areas. (40 Codified Federal Register (CFR) 232, as amended). Wetlands shall be delineated by a site survey approved by the Community using delineation protocols accepted by the U.S. Army Corps of Engineers and the Ohio EPA at the time of application of this regulation. If a conflict exists between the delineation protocols of these two agencies, the delineation protocol that results in the most inclusive area of wetlands shall apply.
(hhh) WETLAND SETBACK: Those lands adjacent to wetlands where earth disturbing activities will not take place and natural vegetation will not be removed.
(iii) WINTER: October 1st to April 1st of each year.
(Ord. 2009-26. Passed 5-20-09.)