8-8-4: CONNECTION CHARGES:
   (A)   Inside City Limits: At the time of making application for water connection to the present water system for use inside the city limits, the applicant shall pay a connection and permit fee for the city to process the application and construct the meter box in an amount established by a resolution adopted by the Burley city council.
For larger meters all installation and materials of the meter shall be subject to approval by the water superintendent. Meters and taps above two inches (2") will be installed, constructed and paid for by the customer according to city specification. The costs of the meter and strainer shall be paid for by the customer. All excavating and backfilling will be completed by the customer and the area restored to its original condition. A permit and inspection fee shall be paid to the city at the time of an application for a disconnect from, or a hookup to, the meter yoke.
   (B)   Outside City Limits: At the time of making application for water connection where water is to be used outside the City limits, the applicant shall pay a connecting and permit fee equal to two (2) times the rate specified in subsection (A) of this section. All services rendered outside the City limits shall be the responsibility of the property owner or user. Meters will be located at a point to be designated by the Superintendent of Water, and the property owner or user shall install all piping and fittings necessary from the City limits to the point of use, and full responsibility for excavations, refilling and materials necessary for installation shall rest with the property owner or user.
   (C)   Fire Connection Fee: The fee for processing the application and connection to the present water system for a fire line shall be in an amount established by a resolution adopted by the Burley City Council per inch (1") of pipe measured on the inside diameter. All work and material shall be subject to approval of the Water Superintendent. (Ord. 1160, 5-7-2002)