9-2-14: COLLECTION AND PENALTIES:
The City may utilize the following means and methods to ensure the payment of impact fees:
   A.   Interest: Charge interest on any unpaid portions of the impact fee with interest at the highest legally allowable rate and a penalty of five percent (5%) for each thirty (30) day period payment is late;
   B.   Building Permit Withheld: Withholding the building permit until the impact fee is paid;
   C.   Utility Service Withheld: Withholding utility services until the impact fee is paid; or
   D.   Lien: Creation of a lien for failure to pay the impact fee following the procedures set forth in Idaho Code title 45, chapter 5. (Ord. 43-16, 12-13-2016, eff. 1-1-2017)