9-12-8: DECONSTRUCTION AND DEMOLITION MATERIAL AND WASTE MANAGEMENT:
   A.   Where buildings, structures, or portions thereof are deconstructed or demolished, applicable individual materials shall be diverted from landfill waste as specified in the Deconstruction and Demolition Material and Waste Management Plan established by Boise City. The building official, or designee, may require independent third-party audit and/or verification where deemed necessary. The Deconstruction and Demolition Material and Waste Management Plan shall be completed by a designated Recycling/Reuse Coordinator, that includes procedures for deconstruction or demolition, and that documents the total materials from sites, buildings, structures, and portions thereof, to be deconstructed or demolished and the materials to be diverted for recycle or reuse purposes, including destinations of diverted materials and hauling method.
   B.   Exceptions:
      1.   Where evidence can be shown that certain types of buildings or structures, or portions thereof, do not have acceptable or adequate materials for recycle or reuse, divert materials to the maximum extent possible, with building official approval.
      2.   Where evidence can be shown that the building or structure, or portion thereof, has excessive damage from conditions such as hazardous materials, fire damage, water damage, rot, mold, etc., may be exempt, with building official approval.
      3.   Buildings or structures, or portions thereof, ordered to be abated under the City Dangerous Buildings Code may be exempt, with building official approval. (Ord. 15-21, 5-4-2021)