§ 155.04 SUBDIVISION APPROVAL PROCESS FOR WHICH PLAT IS REQUIRED.
   The steps required for approval of a subdivision of land in the village for which a plat is required are as follows:
   (A)   Approval of a concept plan as described in §§ 155.05 and 155.06.
   (B)   Approval of a subdivision improvement plan as described in§ § 155.07 through 155.09.
   (C)   Security required for the completion of subdivision improvements as described in § 155.15.
   (D)   Approval of plat of subdivision as described in §§ 155.12 through 155.14.
   (E)   Required guarantee of subdivision improvements as described in § 155.18.
   (F)   Acceptance of public streets or other public improvements as described in § 155.17.
(Ord. C-611, passed 2-9-87)