771.05 COMPLETION.
   A final certificate of occupancy shall not be issued until final grading is complete. Lawn areas must be established, and landscaping shall be installed per the approved landscape plan. A temporary certificate of occupancy maybe issued for a period of up to six (6) months if weather conditions inhibit landscape installation, provided that the developer has submitted a financial guarantee held in an independent escrow account in the amount of one hundred twenty-five percent of the installed cost of landscaping.
(Ord. 41-10. Passed 9-26-11.)