726.09 SUPPLEMENTAL REQUIREMENTS.
   (a)   Privacy for individual principal buildings shall be maintained through the use of landscaping and screening.
   (b)   Street lighting and street signs shall be adequate for the safety and security of residents.
   (c)   Walkways shall be provided to connect the dwelling units to the common areas and to other areas adjacent to the PURD. Walkways shall be constructed of concrete unless otherwise permitted by the Planning Commission.
   (d)   Additional development requirements formulated to achieve the objectives of this section may be established at the time the general development plan is reviewed. Any such development requirements adopted with such plan shall become binding land use requirements for the proposed PURD.
   (e)   PURD approvals.
      (1)   PURD approval to begin construction is valid for one year from the date of issuance of the original building permit.
      (2)   PURD approval to complete all construction is valid for three years from the date of issuance of the original building permit. Should any construction remain incomplete by this three-year timeline, the builder/developer must reappear before the Planning Commission with a new plan.
   (f)   The Architectural Review Board shall review and approve the exterior design of all dwelling units and shall review and approve all common area structures and the comprehensive landscape plan.
(Ord. 14-23. Passed 12-11-23.)