Skip to code content (skip section selection)
Compare to:
CHAPTER 15.18
RENEWABLE ENERGY PROJECTS
SECTION:
15.18.010: Establishment And Purpose
15.18.020: Hearing Process And Noticing
15.18.030: Preapplication Process
15.18.040: Application Process
15.18.050: Application Fee
15.18.060: Criteria For Approval
15.18.070: Appeal Process
15.18.080: Who Can Appeal
15.18.090: Contents Of Appeal
15.18.100: Time Period For Hearing Of Appeal
15.18.110: Action By The Board Of County Commissioners
15.18.120: Effective Date
15.18.130: Special Use Permit Maintenance
15.18.200: Expedited Permit Process For Renewable Energy Generation Projects On Public Lands
15.18.250: Renewable Energy Generation Project Special Use Permit !2R!
15.18.010: ESTABLISHMENT AND PURPOSE:
Pershing County hereby establishes a special use permit process. The purpose of this chapter is to provide a method of reviewing proposed uses, which possess characteristics that require special appraisal in order to determine if the uses have the potential to adversely affect other land uses, air or water quality, transportation systems, or public facilities or services. (Ord. 308, 2014)
15.18.020: HEARING PROCESS AND NOTICING:
The board of Pershing County commissioners shall take action to approve, approve with conditions, modify, modify with conditions, or deny the special use permit request based upon recommendations from the Pershing County regional planning commission. Except as otherwise provided by law, the process shall follow the general provisions of the Pershing County development code for special use permits as part of the approval of a special use permit application in relation to noticing and holding hearings. Failure of the commission to hold a public hearing or take action within the time frames provided in this chapter shall constitute approval of the application.
A hearing to consider an application for a special use permit shall be held within sixty five (65) days after the filing of the application. The hearing must be noticed and conducted according to the provisions set forth in Nevada Revised Statutes 278.315. (Ord. 308, 2014)
15.18.030: PREAPPLICATION PROCESS:
Prior to submitting the application for a special use permit, the applicant must have a presubmission meeting with Pershing County planning and building department staff to discuss the project and the application. No special use permit application shall be accepted and processed until the information necessary to review and decide upon the proposed special use permit is deemed complete. (Ord. 308, 2014)