A. Establishment of Service Areas. There is hereby established a Service Area which Service Area includes all land in the City of Parma.
B. Imposition of Impact Fees. Impact Fees for the City are hereby imposed on all new Development located within the City of Parma.
C. Fee Schedule. Impact Fees shall be calculated in accordance with the fee schedule set forth below providing for standard fees based on the total number of Dwelling Units or square feet of nonresidential space in the Development, unless (a) the Fee Payer requests an individual assessment pursuant to section this Title; or (b) the City finds the Development will have an Extraordinary Impact pursuant to this Title. The methodology for determining the costs per service unit provided for in the fee schedule is set forth in the City's Capital Improvements Plan as adopted by the City pursuant to Idaho Code § 67-8208, as it may be amended.
Parks and Recreation | |
Single-Family (per Dwelling Unit) | $1,342.00 |
Multifamily (per Dwelling Unit) | $556.00 |
Transportation Multimodal | |
Single-Family (per Dwelling Unit) | $722.00 |
Multifamily (per Dwelling Unit) | $300.00 |
Transportation- Roadways | |
Single-Family Residential (per Dwelling Unit) | $474.00 |
Multi-Family Residential (per Dwelling Unit) | $132.00 |
Nonresidential -Retail (per 1000 sq. ft) | $804.00 |
Nonresidential-Office (per 1000 sq. ft.) | $310.00 |
Nonresidential-Industrial (per 1000 sq. ft) | $139.00 |
Non-Residential-Institutional (per 1000 sq. foot) | $558.00 |
Fire Protection | |
Single-Family Residential (per Dwelling Unit) | $1,984.00 |
Multi-Family Residential (per Dwelling Unit) | $825.00 |
Nonresidential -Retail (per 1000 sq. ft) | $4,126.00 |
Nonresidential-Office (per 1000 sq. ft.) | $1,590.00 |
Nonresidential-Industrial (per 1000 sq. ft) | $734.00 |
Non-Residential-Institutional (per 1000 sq. foot) | $3,314.00 |
D. Procedures:
1. Building Permit. Upon submittal of complete building permit plans or manufactured home installation permit for the Development to the City, the City shall calculate the Impact Fee for the Development within thirty (30) days of submittal unless:
a. The Fee Payer had previously requested and been granted an individual assessment pursuant to this chapter; or
b. The City has previously determined the Development may have an Extraordinary Impact pursuant to this chapter.
E. Exemptions. The provisions of this chapter shall not apply to the following:
1. Rebuilding the same amount of floor space of a structure which is destroyed by fire or other catastrophe, provided the structure is rebuilt and ready for occupancy within two (2) years of its destruction;
2. Remodeling or repairing a structure which does not increase the number of Service Units;
3. Replacing a residential unit, including a manufactured/mobile home, with another residential unit on the same lot; provided that, the number of Service Units does not increase;
4. Placing a temporary construction trailer or office on a lot;
5. Constructing an addition on a residential structure which does not increase the number of Service Units;
6. Adding uses that are typically accessory to residential uses, such as tennis court or a clubhouse, unless it can be clearly demonstrated that the use creates a significant impact on the capacity of System Improvements; or
7. The installation of a modular building, manufactured/mobile home or recreational vehicle if the Fee Payer can demonstrate by documentation such as utility bills and tax records that either: (a) a modular building, manufactured/mobile home or recreational vehicle was legally in place on the lot or space prior to the effective date of this chapter; or (b) an Impact Fee has been paid previously for the modular building, manufactured/mobile home or recreational vehicle on that same lot or space.
F. Exemption Claim Process. A Fee Payer shall claim an exempt development activity upon application of a building permit or manufactured/mobile home installation permit, or if no building permit or manufactured/mobile home installation permit required, prior to the time construction commences. Any exemption not so claimed shall be deemed waived by the Fee Payer. Claims for exemption shall be determined by the City within fifteen (15) days of receipt of the claim for exemption. (Ord. 617, 2-14-2023)
A. Payment of Fees. The Impact Fee shall be paid to the City at the following times:
1. If a Building Permit or manufactured/mobile home installation permit is required, then before or at the time the permit is issued;
2. If no Building Permit or manufactured/mobile home installation permit is required, then at the time that construction commences; or
3. At such other time as the Fee Payer or Developer and the City have agreed upon in writing.
B. Enforcement. When any Impact Fee is due pursuant to this chapter, or pursuant to the terms of any written agreement between a Fee Payer and the City, and such Impact Fee has not been paid in a timely manner, the City may exercise any or all of the following powers as applicable to its authority, in any combination, to enforce the collection of the Impact Fee:
1. Withhold Building Permits, manufactured home installation permits, or other City Development Approval related to the Development for which the Impact Fee is due until all Impact Fees due have been paid, and issue stop work orders, and revoke or suspend a Building Permit;
2. Withhold utility services from the Development for which the Impact Fee is due until all Impact Fees due have been paid;
3. Add interest to the Impact Fee not paid in full at the legal rate provided for in Idaho Code § 28-22-104, as it may be amended, plus five percent (5%) beginning on the date at which the payment of the Impact Fee was due until paid in full;
4. Impose a penalty of five percent (5%) of the total Impact Fee (not merely the portion dishonored, late or not paid in full) per month beginning on the date at which the payment of the Impact Fee was due until paid in full; and
5. Impose a lien pursuant to the authority of Idaho Code § 67-8213(4) for failure to timely pay an Impact Fee following the procedures contained in Idaho Code Title 45, Chapter 5. (Ord. 617, 2-14-2023)
A. A Fee Payer may request a written certification of the impact fee schedule or individual assessment which shall establish the impact fee for that Development. Such certification shall establish the Impact Fee so long as there is no material change to the particular Development as identified in the individual assessment application, or the impact fee schedule. A certification may be applied for in the following manner:
1. Requests for certification shall be in writing and made to the City. Within thirty (30) days after receiving such request, the City shall issue a written certification of the amount of the Impact Fee due for the proposed Development. The certification shall include an explanation of the calculation of the Impact Fee including an explanation of factors considered under Idaho Code § 67-8207 and shall also specify the System Improvement(s) for which the Impact Fee is intended to be used. The City shall provide the certification to the Fee Payer. (Ord. 617, 2-14-2023)
A. In lieu of calculating the amount of the Impact Fee using the impact fee schedules in this Title, an individual assessment of Impact Fees is permitted when the Fee Payer demonstrates by clear and convincing evidence that the established Impact Fee is inappropriate.
1. Individual Assessment Process. A Fee Payer may file a written request for an individual assessment of the Development by the City with the City prior to the receipt of a building permit or other necessary approvals or entitlements from the City. A request for an individual assessment process shall involve consideration of studies, data, and any other relevant information submitted by the Fee Payer to adjust the amount of the Impact Fee. If a Fee Payer files a request for the use of an individual assessment, the Fee Payer shall be responsible for retaining a qualified professional to prepare the individual assessment that complies with the requirements of this chapter, at the Fee Payer's expense. The Fee Payer shall bear the burden of proving by clear and convincing evidence that the resulting individual assessment is a more accurate measure of its proportionate share of the cost of System Improvements, based on the City's adopted Level of Service, than the development impact fees that would otherwise be due pursuant to the fee schedule.
a. Each individual assessment request and supporting documentation submitted by the Fee Payer shall be based on the same level of service standards and unit costs for System Improvements used in the City's Capital Improvements Plan, shall use an average cost (not a marginal cost) methodology, and shall document the relevant methodologies and assumptions used.
b. Each individual assessment request delivered to the City may then be accepted, rejected, or accepted with modifications by the City as the basis for calculating the Impact Fee. The criteria for acceptance, rejection or acceptance with modifications shall be whether the individual assessment is a more accurate measure of demand for System Improvements element(s) created by the proposed Development, or the costs of those facilities, than the applicable fee shown in the fee schedule.
c. The City shall issue a written decision within thirty (30) days following receipt of a completed request for individual assessment together with all supporting information from the Fee Payer, so as not to unreasonably delay the Developer's (Fee Payer's) subsequent applications to the City for Building Permits.
d. The decision by the City on an application for an individual assessment shall include an explanation of the calculation of the Impact Fee, shall specify the System Improvement(s) for which the Impact Fee is intended to be used, and shall include an explanation of those factors identified in Idaho Code § 67-8207.
e. If an individual assessment is accepted or accepted with modifications by the City then the Impact Fee due under this chapter for such Development shall be calculated according to such individual assessment. (Ord. 617, 2-14-2023)
A. When a Developer or their predecessor in title or interest has constructed System Improvements of the same category as a Capital Improvements Element, or contributed or dedicated land or money towards the completion of System Improvements of the same category as the Capital Improvements Element, and the City has accepted such construction, contribution or dedication, the City shall issue a credit against the Impact Fees otherwise due for the same Capital Improvements Element in connection with the proposed Development, as set forth in this section, credit shall be issued regardless of whether the contribution or dedication to System Improvements was required by the City as a condition of Development Approval or was offered by the Developer and accepted by the City in writing, and regardless of whether the contribution or dedication was contributed by the Developer or by a local improvement District controlled by the Developer.
B. Credits against an Impact Fee shall not be given for:
1. Project Improvements; or
2. Any construction, contribution or dedication not agreed to in writing by the City prior to commencement of the construction, contribution, or dedication. Credits issued for one Capital Improvements Element may not be used to reduce Impact Fees due for a different capital improvement. No credits shall be issued for System Improvements contributed or dedicated prior to the effective date of this chapter.
C. Valuation of Credit at Present Value:
1. Land. Credit for qualifying land dedications shall, at the Fee Payer's option, be valued at the present value of:
a. One hundred percent (100%) of the most recent assessed value for such land as shown in the records of the City assessor; or
b. That fair market value established by a private appraiser acceptable to the City in an appraisal paid for by the Fee Payer.
2. Improvements. Credit for qualifying acquisition or construction of System Improvements shall be valued by the City at the present value of such improvements based on complete engineering drawings, specifications, and construction cost estimates submitted by the Fee Payer to the City. The City shall determine the amount of credit due based on the information submitted, or, if it determines that such information is inaccurate or unreliable, then on alternative engineering or construction costs acceptable to the City as a more accurate measure of the value of the offered System Improvements to the City
D. When Credits Become Effective:
1. Land. Approved credits for land dedications shall become effective when the land has been conveyed to the City in a form acceptable to the City, at no cost to the City, and has been accepted by the City. Upon request of the Fee Payer, the City shall issue a letter stating the amount of credit available.
2. Improvements. Approved credits for acquisition or construction of System Improvements shall generally become effective when (a) all required construction has been completed and has been accepted by the City, (b) a suitable maintenance and warranty bond has been received and approved by the City, and (c) all design, construction, inspection, testing, bonding, and acceptance procedures have been completed in compliance with all applicable requirements of the City and the state of Idaho. Upon request of the Fee Payer, the City shall issue a letter stating the amount of credit available.
E. Credit Request Process:
1. Request. In order to obtain a credit against an Impact Fee otherwise due, a Fee Payer shall submit to the City a written offer of request to dedicate to the City specific parcels of qualifying land or a written offer to contribute or construct specific System Improvements to the Capital Facilities in accordance with all applicable State or City design and construction standards, and shall specifically request a credit against the type of Impact Fee for which the land dedication or System Improvements is offered.
2. Review. After receipt of the written offer of request for credit, the City shall review the request and determine whether the land or System Improvements offered for credit will reduce the costs of providing Capital Facilities by an amount at least equal to the value of the credit. If the City determines that the offered credit satisfies that criteria and will be acceptable to the City Board of Commissioners, then the credit shall be issued. The City shall complete its review and determination of an application within thirty (30) days after receipt of an application for credit.
3. Credits Exceeding Fee Amounts Due. If the credit due to a Fee Payer pursuant to this Title exceeds the Impact Fee that would otherwise be due from the Fee Payer pursuant to the chapter (whether calculated through the Impact Fee schedule in section 5A-1-3 or through an individual assessment), the Fee Payer may choose to receive such credit in the form of either: (a) a credit against future Impact Fee due for the same System Improvements; or (b) a reimbursement from Impact Fees paid by future Development that impacts the System Improvements contributed or dedicated by the Fee Payer. Unless otherwise stated in an agreement with the Fee Payer, the City shall be under no obligation to use any of the City funds - other than Impact Fees paid by other Development for the same System Improvements - to reimburse the Fee Payer for any credit in excess Impact Fees that are due.
4. Written Agreement Required. If credit or reimbursement is due to the Fee Payer pursuant to this section, the City shall enter into a written agreement with the Fee Payer, negotiated in good faith, prior to the contribution, dedication, or funding of the System Improvements giving rise to the credit. The agreement shall provide for the amount of credit or the amount, time and form of reimbursement, and shall have a term not exceeding ten (10) years.
5. The City's determination on the written offer of request for credit shall be provided to the Fee Payer. (Ord. 617, 2-14-2023)
A. General Provisions.
1. Accounting Principles. The calculation of the Impact Fee shall be in accordance with generally accepted accounting principles. A development impact fee shall not be deemed invalid because payment of the fee may result in an incidental benefit to owners or Developers within the service area other than the Fee Payer.
2. Levels Of Service. The Impact Fee shall be calculated on the basis of levels of service for Public Facilities in the adopted Capital Improvement Plan that are applicable to existing Development as well as new growth and Development. The construction, improvement, expansion or enlargement of new or existing Public Facilities for which the Impact Fee is imposed must be attributable to the capacity demands generated by the new Development.
B. Methodology; Proportionate Methodology. The Impact Fee shall not exceed a proportionate share of the cost of the System Improvements determined in accordance with Idaho Code § 67-8207, as it may be amended. Impact Fees shall be based on actual System Improvements Costs or reasonable estimates of such costs. The amount of the Impact Fee shall be calculated using the methodology contained in the adopted Capital Improvements Plan.
C. Proportionate Share Determination.
1. The Impact Fee shall be based on a reasonable and fair formula or method under which the Impact Fee imposed does not exceed a proportionate share of the costs incurred or to be incurred by the City in the provision of System Improvements to serve the new Development. The proportionate share is the costs attributable to the new Development after the City considers the following:
a. Any appropriate credit, offset or contribution of money, dedication of land or construction of System Improvements;
b. Payments reasonably anticipated to be made by or as a result of a new Development in the form of user fees and debt service payments;
c. That portion of general tax or other revenues allocated by the City to System Improvements; and
d. All other available sources of funding such System Improvements.
2. In determining the proportionate share of the cost of System Improvements to be paid by the Developer, the following factors shall be considered by the City and accounted for in the calculation of the Impact Fee:
a. The costs of existing System Improvements within the Service area;
b. The means by which existing System Improvements have been financed;
c. The extent to which the new Development will contribute to System Improvements Costs through taxation, assessments, or developer or landowner contributions, or has previously contributed to System Improvements Costs through Developer or landowner contributions;
d. The extent to which the new development is required to contribute to the cost of existing System Improvements in the future;
e. The extent to which the new Development should be credited for providing System Improvements, without charge to other properties within the Service Area;
f. Extraordinary costs, if any, incurred in serving the new Development;
g. The time and price differential inherent in a fair comparison of fees paid at different times; and
h. The availability of other sources of funding System Improvements including, but not limited to, user charges, general tax levies, intergovernmental transfers and special taxation. (Ord. 617, 2-14-2023)
A. The City may make an initial determination that Development may impose an Extraordinary Impact due to a review of a development application transmitted to the City pursuant to the City's zoning authority under the Local Land Use Planning Act, chapter 65, title 67, Idaho Code.
B. Process:
1. Within thirty (30) days after City's receipt of the development application, the City will notify the Fee Payer of the City's initial determination that the Development may impose an Extraordinary Impact. Such notice shall include that a supplemental study, at the Fee Payer's expense will be required.
2. Within thirty (30) days following the designation of a Development with Extraordinary Impact, the City shall meet with the Fee Payer to discuss whether the Fee Payer wants to: (a) pay for the supplemental study necessary to determine the System Improvements Costs related to the proposed Development; (b) modify the proposal to avoid generating Extraordinary Impact; or (c) withdraw the application for certification, or Development approval.
3. If the Fee Payer agrees to pay for the supplemental study required to document the proposed Development's proportionate share of System Improvements Costs, then the City and the Fee Payer shall jointly select an individual or organization acceptable to both to perform such study. The Fee Payer shall enter into a written agreement with such individual or organization to pay the costs of such study. Such agreement shall require the supplemental study to be completed within thirty (30) days of such written agreement, unless the Fee Payer agrees to a longer time.
4. Once the study has been completed, the Fee Payer may choose to: (a) pay the proportionate share of System Improvements Costs documented by the supplemental study; or (b) modify the proposed Development to reduce such costs; or (c) withdraw the application.
5. If the Fee Payer agrees to pay the System Improvements Costs documented in the supplemental study, that agreement shall be reduced to writing between the City and the Fee Payer prior to review and consideration of any application for any Development approval or Building Permit related to the proposed Development.
6. Notwithstanding any agreement by the Fee Payer to pay the proportionate share of System Improvements Costs documented by the supplemental study, nothing in this ordinance shall obligate the City to approve Development that results in an Extraordinary Impact to the City. (Ord. 617, 2-14-2023)