931.01   PERMIT FOR INSTALLATIONS.
   (a)   Any utility company desiring to make any installations whatsoever in the City shall first obtain both the approval of, and a permit from, the Director of Public Service.
(Ord. 44-57. Passed 3-4-57.)
   (b)   As a prerequisite to the issuance of a permit by the Director of Public Service for the installation of service equipment by a telephone company, as provided in subsection (a) hereof, the plans and the location must first be given in writing to the Ward Councilman in whose ward such equipment is being installed, and the Director of Public Service shall not issue a permit until he has a receipt in writing from the Ward Councilman acknowledging notification of the proposed location.
   (c)   In addition to the requirements of subsections (a) and (b) hereof, no utility company shall install service equipment upon private property without appropriately landscaping the area where such equipment is installed, if the owner or person in charge of such private property desires such landscaping. Such landscaping shall be subject to the approval of such owner or person in charge.
(Ord. 55-75. Passed 3-3-75.)