Section 105.3.2 of Chapter 1 of the California Building Code is amended to read:
105.3.2 Time limitation of application. An accepted application for a permit for any proposed work shall be deemed to have been abandoned twelve (12) months after the date of filing, unless such application has been pursued in good faith or a permit has been issued; except that the building official is authorized to grant one or more extensions and/or reactivations for additional periods not exceeding ninety (90) days each. The extension shall be required in writing and justifiable cause demonstrated.
(Ord. 5564 § 1 (part), 2022)