(a) Ohio Dam Safety Laws. The provisions of the Ohio Dam Safety Laws shall be followed. Proof of compliance with the Ohio Dam Safety Law administered by the ODNR Division of Water shall be, but is not limited to, a copy of the ODNR Division of Water permit number or a copy of the project approval letter from the ODNR Division of Water or a letter from the site owner explaining why the Ohio Dam Safety Law is not applicable. The written proof will be provided to the City Engineer before a construction permit will be issued.
(b) NPDES Permits. The provisions of the National Pollutant Discharge Elimination System (NPDES) Permits, issued by the Ohio EPA, shall be followed. Proof of compliance shall be, but is not limited to, a copy of the Ohio EPA NPDES Permit number or a letter from the site owner explaining why the NPDES Permit is not applicable. The written proof will be provided to the City Engineer before a construction permit will be issued.
(c) Federal and State Wetland Permits. The provisions of the U.S. Army Corps of Engineers dredge and fill permits for federally-protected wetlands shall be followed. The provisions of Ohio EPA's Isolated Wetlands Permits shall also be followed. Wetlands and other waters of the United States shall be delineated by protocols accepted by the U.S. Army Corps of Engineers and the Ohio EPA at the time of the application of these regulations. Written proof of compliance with both permit programs will be provided to the City Engineer before a construction permit will be issued. Proof of compliance shall be, but is not limited to, the following:
(1) A copy of the U.S. Army Corps of Engineers Individual Permit, if required for the project, showing project approval and any restrictions that apply to site activities; or
(2) A site plan showing that any proposed fill of waters of the United States conforms to the general and specific conditions specified in the applicable Nationwide Permit; or
(3) A letter from the site owner verifying that a qualified professional has surveyed the site and found no wetlands or other waters of the United States. Such a letter shall be noted on site plans submitted to the Community.
(Ord. 77-2004. Passed 6-28-04.)
(a) All permanent storm water, soil erosion, other wastes control, and water quality practices not specifically waived by the Community shall be constructed prior to the granting of the final plat approval. Upon the request of the owner, the Community may defer the construction or installation of a permanent storm water, soil erosion, sediment, or other wastes control or water quality practice prior to the approval of the final plat where, in the City Engineer's judgment, such proper construction or installation is not immediately necessary for the protection of the public health and safety; and where the prior installation or construction of such improvement would constitute an undue hardship on the owner because in the case of new vegetation or weather conditions, or because in the case of concrete, building construction could cause cracking and excessive wear and tear on new structures. In such event, the Community shall require a security bond, escrow account, certified check or cash to guarantee that such deferred improvements will be properly constructed or installed within an agreed specified time, but not to exceed six months after the filing of such final plat.
(b) The owner will provide a maintenance guarantee for all permanent improvements, and soil erosion, wastes controls, and water quality practices.
(c) The Community shall require a security bond, escrow account, certified check or cash to guarantee that the planned temporary and permanent soil erosion, sediment, and other wastes controls and water quality practices will be constructed and removed in a timely manner, as determined by the City Engineer.
(1) The guarantee. The guarantee of both performance and maintenance will be in the form of a security bond, escrow account, certified check or cash. The security bond, escrow account, certified check or cash will be used by the Community to complete any guaranteed construction or removal of improvements or temporary and permanent soil erosion, sediment, and other wastes control practices that are not adequately completed, maintained or removed by the owner in a timely manner, as determined by the City Engineer. The security bond, escrow account, certified check or cash will be in the total amount of both the performance guarantee and the maintenance guarantee. Ohio municipalities and counties may require performance bonds or other guarantees for water management improvement as stated in Ohio R.C. Chapter 711.101.
A. A security bond, escrow account, certified check or cash shall be deposited with the Community prior to review by the City Engineer and/or its consultants to cover professional services of the City Engineer, Building Commissioner, Zoning Inspector and/or other experts required by the City Engineer, Community Council, Mayor or Review Boards.
B. No soil disturbing activities shall be permitted until a security bond, escrow account, certified check or cash has been posted to the satisfaction of the City Engineer sufficient for the Community to perform the obligations otherwise to be performed by the owner or person responsible for the development area as stated in this regulation, and to allow all work to be performed as needed in the event that the owner or person responsible for the development area fails to comply with the provisions of this regulation. The security bond, escrow account, certified check or cash shall be released only after all work required by this regulation has been completed to the satisfaction of the City Engineer and all permit and inspection fees required by these regulations have been paid in full.
C. No project subject to this regulation shall commence without the Construction Site Conservation Plan having been approved by the City Engineer.
(2) Performance guarantee. The furnishing of a performance guarantee will be maintained in an amount of not less than 120% of the estimate approved by the City Engineer, of installation of the deferred improvements.
(3) Maintenance guarantee. The maintenance guarantee shall be maintained for a period of not less than two years after final acceptance of the storm water, soil erosion, sediment, and other wastes control practices in an amount equal to 20% of the estimate approved by the City Engineer, of the construction and, where necessary, removal of such practices.
(4) Time extension. The City Engineer may extend for cause the time allowed for the installation of the improvements for which the performance guarantee has been provided with the receipt of a written request from the owner.
(5) Completion. Upon completion of the construction of improvements or temporary and/or permanent, soil erosion, sediment, and other wastes control practices and the removal of the temporary soil erosion, sediment, and other wastes control practices for which the performance guarantee has been provided the owner shall notify the City Engineer of this fact.
(6) Inspection. The Community will not release the security bond, escrow account, certified check or cash guarantee until the City Engineer has inspected the site to ensure that the guaranteed item(s) have been completed and/or removed.
(7) Slow release devices. Performance and maintenance guarantees will be maintained on the temporary sediment removal slow release devices installed in detention and retention basins until the entire site has reached final soil stabilization. Final stabilization in single-family residential developments is when 90% of the homes are constructed with their lawns completely installed and any remaining unbuilt lots having been permanently stabilized with a uniform ground cover at a growth density of 80% or better.
(8) Release. The construction maintenance guarantee shall not be released by the Community until all temporary soil erosion and sediment control practices that are no longer needed have been removed, properly disposed of and any trapped sediment has been stabilized.
(Ord. 77-2004. Passed 6-28-04.)
(a) This plan will be combined with the Post-Construction Water Quality, Riparian Setback and Wetland Setback Plans that have also been developed for the site.
(b) Plans developed by the site owners and approved by the Community in accordance with this regulation do not relieve the site owner of responsibility for obtaining and complying with all other necessary permits and/or approvals from Federal, State, County, and local agencies and departments. If requirements vary, the most stringent requirement shall be followed. Plans submitted to the City Engineer for review and approval, shall be accompanied by all other required permits and documentation relevant to the project, including but not limited to the permits required and issued by the U.S. Army Corps of Engineers, Ohio EPA and ODNR Division of Water.
(c) The application must include a letter or report from the local county SWCD that states that the Construction Site Conservation Plan, the Riparian and Wetland Setback Plan and the Post-construction Water Quality Plan have been reviewed for consistency with Ohio EPA and local regulations.
(d) Five sets of the plans and necessary data required by this regulation shall be submitted to the Community Engineer with text material being submitted on 8.5 by 11 inch paper and drawings on no larger than 24 by 36 inch sized paper. Submittals shall include:
(1) At the preliminary plan approval request, the preliminary plans only need to show all of the following existing and planned features: streams, water bodies, wetlands, riparian and wetland setback areas, permanent BMPs and storm water management detention and retention basins.
(2) At the improvement plan approval request, the entire Comprehensive Storm Water Management Plan must be submitted.
(e) The City Engineer shall review the plans, including the review report from the local county SWCD, and shall approve or return these with comments and recommendations for revisions within 30 working days after receipt of the plan as described above. A plan rejected because of deficiencies shall receive a report stating specific problems. At the time of receipt of a revised plan, another 30-day review period shall begin.
(f) Approved plans shall remain valid for two years from the date of approval. After two years the plan(s) approval automatically expires.
(g) No soil disturbing activity shall begin before all necessary local, County, State and Federal permits have been granted to the owner or operator.
(h) The Community will do construction inspections until the site reaches final stabilization as determined by the City Engineer.
(Ord. 77-2004. Passed 6-28-04.)
No person shall violate, or cause, or knowingly permit to be violated, any of the provisions of these regulations, or fail to comply with any such provisions or with any lawful requirements of any public authority made pursuant to these regulations, or knowingly use or cause or permit the use of any lands in violation of these regulations or in violation of any permit granted under these regulations.
(Ord. 77-2004. Passed 6-28-04.)
(a) Whoever violates or fails to comply with any provision of this regulation is guilty of a misdemeanor of the first degree and shall be fined no more than one thousand dollars ($1,000.00) or imprisoned for no more than 180 days, or both, for each offense.
(b) A separate offense shall be deemed committed each day during or on which a violation or noncompliance occurs or continues.
(c) Upon notice from the City Engineer, or designated representative, that work is being performed contrary to this regulation, such work shall immediately stop. Such notice shall be in writing and shall be given to the owner or person responsible for the development area, or person performing the work, and shall state the conditions under which such work may be resumed; provided, however, in instances where immediate action is deemed necessary for public safety or the public interest, the City Engineer may require that work be stopped upon verbal order pending issuance of the written order.
(d) The imposition of any other penalties provided herein shall not preclude the Community, by or through its Law Director and/or any of their assistants, from instituting an appropriate action or proceeding in a Court of Proper Jurisdiction to prevent an unlawful development or to restrain, correct or abate a violation, or to require compliance with the provisions of this regulation or other applicable laws, or ordinances, rules or regulations or the orders of the City Engineer.
(Ord. 77-2004. Passed 6-28-04.)