§ 5-2-1-11. PERMIT ISSUANCE PROCEDURES.
   (A)   Issuance. Upon receipt of a completed application pursuant to this chapter, approval of the worksite and payment of permit fees as specified, the City Engineer may issue a permit to the applicant. The City Engineer may issue an emergency permit (by authorizing the work to proceed and assignment of a permit number) prior to receipt of the application and other required documentation, provided the application is submitted on the following business day.
   (B)   Duration. In general, the permit shall be valid for a 60 calendar-day period unless specified otherwise on the permit, beginning on the day of issuance. Upon a permit holder's justified request, the permit may be extended for an additional 60 calendar-day period or until final restoration has been achieved.
   (C)   Activation. Permit work once approved shall commence within three working days. If for any reason the permit holder determines he or she will be unable to perform work as scheduled, the permit holder shall immediately notify the City Engineer.
(Am. Ord. 15, 2020, passed 12-7-2020) Penalty, see § 1-1-2-3