1333.09 USE OF PUBLIC ROADS.
   (a)   The applicant shall identify all state and local public roads to be used within the City to transport equipment and parts for construction, operation or maintenance of the wind energy facility.
   (b)   The City Engineer or a qualified third party engineer hired by the City and paid for solely by the applicant, shall document road conditions prior to construction. The City Engineer, or the qualified third party engineer, shall document road conditions again thirty (30) days after construction is complete or as weather permits.
   (c)   The City may request a bond for the road in compliance with the City's Code, and in an amount as determined by the City's Engineer.
   (d)   Any road damage caused by the applicant or its contractors shall be promptly repaired at the applicant's expense.
   (e)   The applicant shall demonstrate that it has appropriate financial assurance to ensure the prompt repair of damaged roads.
(Ord. 2009-30. Passed 8-11-09.)