(a) Notice of commencement of work. At least three working days before the work is started, the permittee or the permittee’s representative shall give notice of the time of commencement of the work to the chief engineer or the chief engineer’s representative.
(b) Prosecution of work. After the work has begun, it shall be diligently and continuously prosecuted until completed. All work shall be completed within the time specified in the permit, unless an extension of time for good cause shown is granted by the chief engineer.
(c) Inspection. All work authorized under Articles 2 through 7 of this chapter shall be subject to inspection by the chief engineer or the chief engineer’s authorized representative.
(Sec. 20-1.2, R.O. 1978 (1983 Ed.)) (1990 Code, Ch. 14, Art. 17, § 14-17.2)