When a proposed project requires more than one approval to be lawfully completed, the applicant may apply for all approvals concurrently according to the procedures provided in this section.
(a) The applicant shall submit a one-stop permit application package (OSP) to the director for processing. The OSP shall consist of:
(1) A completed OSP master application form;
(2) All information required for the individual permits or approvals that the applicant is seeking; and
(3) Other information as may be required by the director.
(b) Upon acceptance of the completed OSP, the director shall designate a project manager from within the department to coordinate the review and processing of the individual permit or approval applications comprising the OSP. The project manager shall act as the primary contact person between the director and the applicant concerning the proposed project.
(c) The individual permit or approval applications that comprise the OSP must comply with and shall be processed by the department in accordance with all applicable requirements of this chapter, subject to subsection (d).
(d) The department will process the OSP within the time provided in this article for the individual permit or approval application contained in the OSP that has the longest processing time.
(e) In the event the OSP contains:
(1) One or more permit or approval applications that require council approval; and
(2) One or more permit or approval applications that require only the director’s approval;
the director may approve those applications requiring only the director’s approval subject to the condition that all other applications requiring council approval are duly approved by the council.
(1990 Code, Ch. 21, Art. 2, § 21-2.50) (Added by Ord. 99-12)