1. Wastewater Discharge Permit Duration. A wastewater discharge permit shall be issued for a specified time period, not to exceed 5 years from the effective date of the permit. A wastewater discharge permit may be issued for a period less than 5 years at the discretion of the Township Manager. Each wastewater discharge permit will indicate a specific date upon which it will expire. The user shall apply for permit reissuance at least 180 days prior to the expiration of the user's existing permit.
2. Wastewater Discharge Permit Contents. A wastewater discharge permit shall include such conditions as are deemed reasonably necessary by the Township Manager to prevent pass through or interference, protect the quality of the water body receiving the treatment plant's effluent, protect worker health and safety, facilitate sludge management and disposal, and protect against damage to the POTW.
A. Wastewater discharge permits must contain:
(1) A statement that indicates wastewater discharge permit duration, which in no event shall exceed 5 years.
(2) A statement that the wastewater discharge permit is nontransferable without prior notification to the Township in accordance with § 18-605(5) of this Part, and provisions for furnishing the new owner or operator with a copy of the existing wastewater discharge permit.
(3) Effluent limits based on applicable pretreatment standards.
(4) Self monitoring, sampling, reporting, notification and record keeping requirements. These requirements shall include an identification of pollutants to be monitored, sampling location, sampling frequency and sample type based on Federal, State and local law.
(5) A statement of applicable civil and criminal penalties for violation of pretreatment standards and requirements, and any applicable compliance schedule. Such schedule may not extend the time for compliance beyond that required by applicable Federal, State or local law.
B. Wastewater discharge permits may contain, but need not be limited to, the following conditions:
(1) Limits on the average and/or maximum rate of discharge, time of discharge and/or requirements for flow regulation and equalization.
(2) Requirements for the installation of pretreatment technology, pollution control or construction of appropriate containment devices, designed to reduce, eliminate or prevent the introduction of pollutants into the treatment works.
(3) Requirements for the development and implementation of spill control plans or other special conditions including management practices necessary to adequately prevent accidental, unanticipated or nonroutine discharges.
(4) Development and implementation of waste minimization plans to reduce the amount of pollutants discharged to the POTW.
(5) The unit charge or schedule of user charges and fees for the management of the wastewater discharged to the POTW.
(6) Requirements for installation and maintenance of inspection and sampling facilities and equipment.
(7) A statement that compliance with the wastewater discharge permit does not relieve the permittee of responsibility for compliance with all applicable Federal and State pretreatment standards, including those which become effective during tile term of the wastewater discharge permit.
(8) Other conditions as deemed appropriate by the Township Manager to ensure compliance with this Part, and State and Federal laws, rules and regulations.
3. Wastewater Discharge Permit Appeals. The Township Manager shall provide public notice of the issuance of a wastewater discharge permit. Any person, including the user, may petition the Township Manager to reconsider the terms of a wastewater discharge permit within 30 days of notice of its issuance.
A. Failure to submit a timely petition for review shall be deemed to be a waiver of the administrative appeal.
B. In its petition, the appealing part must indicate the wastewater discharge permit provisions objected to, the reasons for this objection and the alternative condition, if any, it seeks to place in the wastewater discharge permit.
C. The effectiveness of the wastewater discharge permit shall not be stayed pending the appeal.
D. If the Township Manager fails to act within 30 days, a request for reconsideration shall be deemed to be denied. Decisions not to reconsider a wastewater discharge permit, not to issue a wastewater discharge permit or not to modify a wastewater discharge permit shall be considered final administrative actions for purposes of judicial review.
E. Aggrieved parties seeking review of the final administrative wastewater discharge permit decision may appeal to the Industrial Waste Hearing Board.
4. Wastewater Discharge Permit Modification. The Township Manager may modify a wastewater discharge permit for good cause including, but not limited to, the following reasons:
A. To incorporate any new or revised Federal, State or local pretreatment standards or requirements.
B. To address significant alterations or additions to the user's operation, process or wastewater volume or character since the time of wastewater discharge permit issuance.
C. A change in the POTW that requires either a temporary or permanent reduction or elimination of the authorized discharge.
D. Information indicating that the permitted discharge poses a threat to the POTW, personnel or the receiving waters.
E. Violation of any terms or conditions of the wastewater discharge permit.
F. Misrepresentations or failure to fully disclose all relevant facts in the wastewater discharge permit application or in any required reporting.
G. Revision of or a grant of variance from categorical pretreatment standards pursuant to 40 CFR § 403.13.
H. To correct typographical or other errors in the wastewater discharge per
I. To reflect a transfer of the facility ownership or operation to a new owner or operator.
(Note: Modification for this purpose may not be allowed unless the permit is transferable as provided in § 18-605(5)).
5. Wastewater Discharge Permit Transfer. Wastewater discharge permits may be transferred to a new owner or operator only if the permittee gives at least 90 days advance notice to the Township Manager and the Township Manager approves the wastewater discharge permit transfer. The notice to the Township Manager must include a written certification by the new owner or operator which:
A. State that the new owner and/or operator has no immediate intent to change the facility's operations and processes.
B. Identifies the specific date on which the transfer is to occur.
C. Acknowledges full responsibility for complying with the existing wastewater discharge permit. Failure to provide advance notice of a transfer renders the wastewater discharge permit as of the date of facility transfer.
6. Wastewater Discharge Permit Revocation. The Township Manager may revoke a wastewater discharge permit for good cause including, but not limited to, the following reasons:
A. Failure to notify the Township Manager of significant changes to the wastewater prior to the changed discharge.
B. Failure to provide prior notification to the Township Manager of changed conditions pursuant to § 18-606(5) of this Part.
C. Misrepresentation or failure to fully disclose all relevant facts in the wastewater discharge permit application.
D. Falsifying self-monitoring reports.
E. Tampering with monitoring equipment.
F. Refusing to allow the Township Manager timely access to the facility premises and records.
G. Failure to meet effluent limitations.
H. Failure to pay fines.
I. Failure to pay sewer charges.
J. Failure to meet compliance schedules.
K. Failure to complete a wastewater survey or the wastewater discharge permit application.
L Failure to provide advance notice of the transfer of business ownership of a permitted facility.
M. Violation of any pretreatment standard or requirements, or any terms of the wastewater discharge permit or this Part.
Wastewater discharge permits shall be voidable upon cessation of operations or transfer of business ownership. All wastewater discharge permits issued to a particular user are void upon the issuance of a new wastewater discharge permit to that user.
7. Wastewater Discharge Permit Reissuance. A user with an expiring wastewater discharge permit shall apply for wastewater discharge permit reissuance by submitting a complete permit application, in accordance with § 18-604(5) of this Part, a minimum of 180 days prior to the expiration of the user's existing wastewater discharge permit.
8. Regulation of Waste Received from Other Jurisdictions.
A. If another municipality, or user located within another municipality, contributes wastewater to the POTW, the Township shall enter into an intermunicipal agreement with the contributing municipality.
B. The Township Manager shall request the following information from the contributing municipality:
(1) A description of the quality and volume of wastewater discharged to the POTW by the contributing municipality.
(2) An inventory of all users located within the contributing municipality that are discharging to the POTVV.
(3) Such other information as the Township Manager may deem necessary.
C. An intermunicipal agreement, as required by subsection (A), above, shall contain the following conditions:
(1) A requirement for the contributing municipality to adopt a sewer use ordinance which is at least as stringent as this Part and local limits which are at least as stringent as those set out in § 18-602(4) of this Part. The requirements shall specify that such ordinance and limits must be revised as necessary to reflect changes made to the City's Ordinance or local limits.
(2) A requirement for the contributing municipality to submit a revised user inventory on at least an annual basis.
(3) A provisions specifying which pretreatment implementation activities, including wastewater discharge permit issuance, inspection and sampling, and enforcement, will be conducted by the contributing municipality; which of these activities will be conducted by the Township Manager and which of these activities will be conducted jointly by the contributing municipality and the Township Manager.
(4) A requirement for the contributing municipality to provide the Township Manager with access to all information that the contributing municipality obtains as part of its pretreatment activities.
(5) Limits on the nature, quality and volume of the contributing municipality's wastewater at the point where is discharges to the POTW.
(6) Requirements for monitoring the contributing municipality's discharge.
(7) A provisions ensuring the Township Manager access to the facilities or users located within the contributing municipality's jurisdictional boundaries for the purpose of inspection, sampling and any other duties deemed necessary by the Township Manager.
(8) A provisions specifying remedies available for breach of the terms of the intermunicipal agreement.