Upon receipt of the certification by the Commission, the Council shall, within 60 days, either approve or disapprove the final plat.
1. Disapproval of Plat. In the event that said plat is disapproved by the Council, such disapproval shall be expressed in writing and shall point out wherein said proposed plat is objectionable.
2. Acceptance of Plat. In the event that said plat is found to be acceptable and in accordance with these regulations, the Council shall accept same.
3. Final Approval and Recording of Plat. The passage of a resolution by the Council accepting the plat shall constitute final approval of the platting of the area shown on the final plat, but the subdivider or owner shall cause such plat to be recorded in the office of the County Recorder of the county where the land to be subdivided is located, and shall file satisfactory evidence of such recording in the office of the Clerk before the City shall recognize the plat as being in full force and effect.
The following requirements shall govern the re-subdividing of land.
1. Procedure for Re-Subdividing. For any change in a map of an approved or recorded subdivision plat, if such change affects any street layout shown on such map, or area reserved for public use indicated on the map, or any lot line, or if it affects any map or plan legally established prior to the adoption of any regulations controlling subdivisions, such parcel shall be approved by the same procedure, rules, and regulations as for a subdivision.
2. Acreage Lots. Whenever a parcel of land is subdivided and the subdivision plat shows one or more lots containing more than one acre of land and there are indications that such lots will eventually be re-subdivided into smaller building sites, the Commission and Council may require that such parcel of land allow for future opening of streets and the ultimate extension of adjacent streets. Easements providing for the future opening and extension of such streets may be made a requirement of the plat.
Before the final plat is approved by the Council, all applicants shall be required to complete, in accordance with the Council’s decision and to the satisfaction of the City Engineer, all the street, sanitary, and other improvements as required in these regulations, specified in the preliminary plat, and as approved by the Council, and to dedicate same to the City, free and clear of all liens and encumbrances on the property and public improvements thus dedicated.
The Council in its discretion may waive the requirement that the applicant complete and dedicate all public improvements prior to approving the final plat, and that, as an alternative, the applicant post a bond at the time of application for final plat approval in an amount estimated by the Council as sufficient to secure to the City the satisfactory construction, installation, and dedication of the incomplete portion of required improvements. In addition:
1. Approved by City Attorney. Such performance bond shall comply with all statutory requirements and shall be satisfactory to the City Attorney as to form, sufficiency, and manner of execution as set forth in these regulations.
2. Completion Period. The period within which required improvements must be completed shall be specified by the Council in the resolution approving the final plat shall be incorporated in the bond, and shall not exceed one year from date of final approval.
3. Extension of Completion Period. The performance bond shall be approved by the Council as to the amount and surety and conditions satisfactory to the Council. The Commission may, upon proof of difficulty, recommend to the Council extension of the completion date set forth in such bond for a maximum period of one additional year. The Council may at any time during the period of such bond accept a substitution of principal or sureties on the bond.
4. Temporary Improvements. The applicant shall build and pay for all costs of temporary improvements required by the Council and shall maintain same for the period specified by the Council. Prior to construction of any temporary facility or improvement, the developer shall file with the City a separate suitable bond for temporary facilities, which bond shall insure that the temporary facilities will be properly constructed, maintained and removed.
5. Failure to Complete Improvement. For subdivisions for which no performance bond has been posted, if the improvements are not completed within the period specified by the Council in the resolution approving the plat, the approval shall be deemed to have expired. In those cases where a performance bond has been posted and required improvements have not been installed within the terms of such performance bond, the City may declare the bond to be in default and require that all the improvements be installed regardless of the extent of the building development at the time the bond is declared to be in default.
The Council shall provide for inspection of required improvements during construction and insure their satisfactory completion. The applicant shall pay to the City an inspection fee equal to the actual cost of inspection. These fees shall be due and payable upon demand of the City and no building permits or certificates of occupancy shall be issued until all fees are paid. The subdivider shall furnish the Council with a construction schedule prior to the commencement of any and all construction, and notify the City not less than 24 hours in advance of readiness for required inspections.