The size, slope, alignment, materials of construction of all sanitary sewers including building sewers, and the methods to be used in excavating, placing of the pipe, jointing, testing, and backfilling the trench, shall conform to the requirements of the building and plumbing code or other applicable rules and regulations of the city.
In the absence of suitable code provisions or in amplification thereof, the materials and procedures set forth in appropriate specifications of the A.S.T.M. and W.P.C.F. Manual of Practice No. 9 shall apply.
(Ord. 360 Art. IV, § 6, 1980).
Whenever possible, the building sewer shall be brought to the building at an elevation below the basement floor. In all buildings in which any building drain is too low to permit gravity flow to the public sewer, sanitary sewage carried by such building drain shall be lifted by an approved means and discharged to the building sewer.
(Ord. 360 Art. IV, § 7, 1980) .
No person(s) shall make connection of roof downspouts, foundation drains, areaway drains, or other sources of surface runoff or groundwater to a building sewer or building drain which in turn is connected directly or indirectly to a public sanitary sewer unless such connection is approved by the director of public works for purposes of disposal of polluted surface drainage.
(Ord. 360 Art. IV, § 8, 1980).
Loading...