1115.11 APPLICATION FOR APPROVAL OF FINAL PLAT.
   Any Owner/Developer, upon determining to proceed with a final plat, shall submit six (6) complete sets of drawings and materials as specified in Section 1115.12 below to the Zoning Inspector. The applicant shall submit all fees as applicable for a final plat, as established by City Council. Within ten (10) business days, the Zoning Inspector shall review the application, and determine if such application is complete and if all applicable requirements of this Ordinance have been met. If the Zoning Inspector determines that all applicable requirements have been met, the Zoning Inspector shall transmit the application to the Planning Commission at its next regularly scheduled meeting, which shall be deemed the date of submission of the final plat.
(Ord. 27-11. Passed 3-14-11.)