15-28-1130  Construction of grain bleachers.
   Every grain bleacher shall be of Type IA construction. No combustible construction shall be used between a grain bleacher and any other building.
(Prior code §  92-102)
15-28-1140  Construction of cereal, feed, flour, grist and starch mills.
   Every building, or part of a building, designed, erected, altered or converted for the purposes of a cereal mill, feed mill, flour mill, grist mill, or starch mill and in which more than 500 pounds of any cereal, feed, flour, grist or starch is produced during any 24-hour period shall be of Type IA, IB or IC construction.
(Prior code §  92-103)
15-28-1150  Construction of grain elevators and malt houses.
   Every grain elevator, malt house and similar building shall be of Type IA construction.
(Prior code §  92-104)
15-28-1160  Marine tower.
   In any existing grain elevator, malt house or similar building, the exterior walls of the marine tower, which is defined as that part of the structure in which is located the machinery for conveying grain from boats to the conveying bridge, and thence to the bins; and the exterior walls of cupolas and conveyor bridge, which is that part of the structure housing the conveying and elevating machinery above the fireproof bins, may, if the same require replacement, be replaced with galvanized corrugated steel, protected metal or asbestos corrugated material fastened to the steel structure by rust-proof bolts.
(Prior code §  92-105)
15-28-1170  Bleaching operations.
   (a)   Storage. Sodium peroxide and sulfur in excess of one day's supply shall be stored in a separate and suitable building. The user shall notify the fire prevention bureau, by notarized letter, of the amount used in 24 hours. Upon any change in that amount, the user shall notify the fire prevention bureau within 24 hours.
   (b)   Construction of Pots. Sulfur pots shall be so constructed that if the sulfur boils over it cannot drop on combustible material. In broom corn factories, metal hoods shall be provided to prevent corn falling into or against the pots.
   (c)   Location of Grain Bleachers. Grain bleachers shall be set at least 25 feet from frame grain elevators but may be set not closer than six feet to a brick or fireproof elevator; provided, however, there are no unprotected openings in the elevator wall within 25 feet of the bleacher. Metal spouts connecting the bleacher with the elevator shall each be provided with two automatic dampers, one damper at each end of metal spout. All conveyors connecting the bleacher with the elevator shall be metal screw conveyors in metal or concrete casings. No combustible material shall be used between bleacher and elevator.
   (d)   Location of Sulfur Furnace. The sulfur- burning furnace shall be set at least 25 feet distant from bleacher in the opposite direction from the elevator and shall be of fireproof construction and unenclosed, unless it be an enclosure of fireproof construction; provided, however, that when conditions are such that the sulfur furnace cannot be located 25 feet from the bleacher, it may be located closer, but the length of the sulfur fumes pipe shall in no case be less than 25 feet.
(Prior code §  92-106)