1109.07 CONSTRUCTION OF BUILDINGS.
   Construction of buildings shall not be permitted until all improvements are completed and accepted by the Village. (Ord. 1973-10. Passed 1-8-74.)
1109.08 TIME FOR CONSTRUCTION OF IMPROVEMENTS.
   All required improvements shall be constructed within two years of the acceptance of the final plat by Council. (Ord. 1973-10. Passed 1-8-74.)
1109.09 STREET CONSTRUCTION.
   Streets shall be graded to full width of the right-of-way and fully constructed in accordance with the Construction and Material Specifications of the Village in effect at the time the improvements are made. (Ord. 1973-10. Passed 1-8-74.)
1109.10 WATER SUPPLY.
   Where a public water supply main is reasonably accessible, in the judgment of the Planning Commission, the subdivision shall be provided with a complete loop type water distribution system adequate to serve the area being platted, including a connection for each lot and fire hydrants spaced in accordance with the requirements of the National Board of Fire Underwriters. Where public water supply is not available within a reasonable distance, the average size of the lots shall be not less than 20,000 square feet. The entire water system shall be designed to meet the approval of the Engineer. (Ord. 1973-10. Passed 1-8-74.)
1109.11 STORM DRAINAGE.
   Every subdivision shall be provided with a storm water sewer or drainage system adequate to serve the area being platted and otherwise meeting the approval of the Engineer.