1330.04 GENERAL REQUIREMENTS.
   (a)   All sewers shall be bulkheaded below slab or basement floor or outside footer. An authorized agent of the Department of Building shall inspect bulkheading.
   (b)   All demolition debris shall be removed from site including all slab, basement walls and floors, footers and any other sub-grade structures.
   (c)   All basements or other excavations resulting from demolition shall be backfilled with clean sandy fill (sand, clay or loam) to existing grade. All backfill is subject to inspection and approval by the Department of Building prior to backfilling.
   (d)   No excavating shall be made on the job for the purpose of removing soil or burying debris. All excess debris shall be removed from premises and properly disposed.
   (e)   In the event the contractor shall bury debris on the site he shall be responsible for removal of said debris at his own expense. If the contractor fails to remove said debris the city shall take whatever steps are required to re-excavate and properly dispose of improperly buried debris. This includes the hiring of another contractors and any costs shall be incurred by the original contractor responsible for the violation.
   (f)   No demolition work shall be performed on Saturday, Sunday or legal holiday's without the expressed consent of the Department of Building.
(Ord. 8920-2002. Passed 9-3-02.)