1921.07 REZONING: TIME LIMITATIONS ON CONSTRUCTION.
   The owner of rezoned property shall obtain a building permit within one year (1 yr.) of the date of enactment of the rezoning ordinance and shall begin construction under such permit no later than six months (6 mos.) after the issuance of the permit. Failure to comply with these time limitations shall cause the property to revert to the former classification. For good cause the Planning Commission may extend these periods of time. Land rezoned as part of a Master Plan by Council or land rezoned at the request of Council for the benefit of the City as a whole shall not be affected.
(Ord. 7139-99. Passed 7-6-99.)