1349.07 EXPIRATION OF PERMIT.
   A demolition permit will expire if the work is not started within 90 days and is not completed within one year. Extensions may be granted beyond one year in 60 day increments for large or phased demolition projects or upon a showing by the applicant that work has been delayed for reasons beyond the applicant's control.