The City Engineer shall inspect the field delineation of riparian zones.
(a) Field delineations of riparian zones required by this chapter shall be made prior to soil-disturbing activities authorized by the City Engineer under a subdivision or land development plan. The applicant shall provide the City Engineer with at least two working days notice prior to starting such soil-disturbing activities. Construction fences, as prescribed by this chapter and which serve to delineate riparian zone areas, must be installed prior to the issuance of two working days notice to the City Engineer.
(b) Prior to activities authorized by the City Engineer under Section 1051.05 of this regulation. The applicant shall provide the City Engineer with at least two working days notice prior to starting such activities.
(Ord. 75-15. Passed 7-13-15.)