932.33 COMPLIANCE SCHEDULES.
Where additional pretreatment and/or operation and maintenance activities are required to comply with these Regulations the District shall develop or require the discharger to develop a compliance schedule enumerating the methods, such processes and shortest reasonable times within which such objectives are to be met.
The compliance schedules shall specifically address the additional pretreatment and/or operation and maintenance activities, the dates for commencement and completion of the same, and all applicable engineering and other factors pursuant to 932.15(i) and other concerns the District requires.
Within fourteen days following each milestone date in the compliance schedule, and the final date for compliance, the discharger shall submit a compliance schedule report consistent with the substantive requirements of 932.15.
(Ord. 92-206. Passed 4-29-92.)