Sec. 6-19.702.   Installation permit and review requirements for alternative systems.
   (a)   General requirements for site evaluation and for obtaining an installation permit are prescribed in Article 6 of this chapter and in the Manual.
   (b)   An alternative system design shall be prepared and signed or stamped by a qualified system designer. The qualified system designer shall also be responsible for inspections of the system installation to assure conformation with approved plans.
   (c)   System design will be reviewed by DEH and, where warranted, such as due to the complexity of the system, DEH may refer the plans to the California Central Valley Regional Water Quality Control Board staff and/or external third-party expert consultant(s) for additional review, the costs for which would be the responsibility of the applicant.
(Ord. 1469, eff. July 14, 2016)