Sec. 10-8.406.   Cultural resources.
   Damaging effects on cultural resources shall be avoided whenever possible. If avoidance is not feasible, the importance of the site shall be evaluated by a qualified professional prior to the commencement of mining operations. If a cultural resource is determined not to be important, both the resource and the effect on it shall be reported to the Agency, and the resource need not be considered further. If avoidance on an important cultural resource is not feasible, a mitigation plan shall be prepared and implemented. The mitigation plan shall explain the importance of the resource, describe the proposed approach to mitigate destruction or damage to the site, and demonstrate how the proposed mitigation would serve the public interest.
   If human skeletal remains are encountered during mining, all work within seventy-five (75) feet shall immediately stop, and the    County Coroner shall be notified within twenty-four (24) hours. If the remains are of Native American origin, the appropriate Native American community identified by the Native American Heritage Commission shall be contacted, an agreement for treating or disposing of, with appropriate dignity, the remains and associated grave goods shall be developed. If any cultural resources, such as chipped or ground stone, historic debris, building foundations, or paleontological materials are encountered during mining, then all work within seventy-five (75) feet shall immediately stop and the Director shall be notified at once. Any cultural resources found on the site shall be recorded by a qualified archaeologist and the information shall be submitted to the Agency. (§ 2, Ord. 1276, eff. December 6, 2001)