(A) An inspector shall be required during construction as required by the Village Engineer. The Village Engineer shall be notified by phone at least 24 hours before any phase of construction is started.
(B) Quality control, laboratory analysis, testing of all materials, and borings shall be provided by an approved testing laboratory, at the developer's expense, as required, by the Village Engineer.
(C) Upon completion of the improvements, the Village Engineer shall meet with the contractors and the developer, subdivider, builder. All improvements shall be thoroughly inspected and all defects noted. Upon correction of these items and posting of $2,000 cash or 5% of total construction cost, whichever is greater, and submission of contractor's final affidavits, the Village Engineer will recommend acceptance to the Village Board.
(D) Prior to final acceptance by the Village Board, it may be necessary to make emergency interim repairs to the underground or surface improvements. The village shall notify the developer, subdivider, builder and it shall be the developer's, subdivider's, builder's responsibility to see that these repairs are made within 24 hours of notification. If these repairs are not accomplished during this period, the village may make the repairs and charge their cost against the developer's, subdivider's, builder's cash deposit.
(E) After the improvements have been installed and approved for 12 months, a final inspection shall be made by the Village Engineer. This inspection will cover all improvements and lot grading. Upon correction of any defects, the balance of the cash deposit shall be returned to the developer, subdivider, builder and the maintenance of the improvements shall become the responsibility of the village.
(Ord. 1995-0-25, passed 12-26-95)