A. Failure to complete project. The Village Council shall consider revocation of the planned development if construction falls more than one year behind the construction schedule filed with the final plat. The applicant shall be notified at least ninety days preceding any revocation proceeding. The Village Council may, upon request, modify the recorded construction schedule of a planned development.
B. Failure to comply with approved plans. Failure to maintain such conditions or restrictions as may have been imposed shall constitute grounds for revocation of the planned development pursuant to Chapter 17.72 of the Village Code.
(MC-2-2019, Amended, 04/25/2019; MC-8-2005, Added, 12/20/2005)